HL incident on 2013-07-09 — MT
Operator
Cenex Pipeline Llc
Cause
Notification Issue
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$30,000
Incident datetime
2013-07-09 15:02
Report number
Location
MT
Narrative
On july 9, 2013, cenex pipeline was delivering product into the glendive terminal with the balance pumping to minot, nd at a rate of approximately 1100 barrels per hour. At approximately 3:02 p.M. Mdt, the cenex pipeline controller noticed a significant pressure drop at the discharge of glendive terminal and arnegard station. The controller began to shut down the 8 inch diameter pipeline segment between glendive and minot as a result of an unexplained pressure drop and had the pipeline shutdown and rov's closed by 3:05 and 25 seconds. At approximately 3:11 p.M., a representative of the excavator phoned the control center to report that their company may have hit the pipeline during excavation and believe that it is damaged. The excavator reported the approximate location of the release in the area between alexander and arnegard in section 26 and 27. The puncture occurred near cenex pipeline mile post 81, and a photograph of the damaged pipe is included in exhibit section 7. Cenex pipeline estimates that 870 barrels of gasoline was released at the site with approximately 38 barrels of free product being recovered. The released product did not ignite, did not reach any surface water, and there were no reported injuries or fatalities as a result of this release. The cause of this damage was determined to be excavator failure to notify the one call center of a change in location of the excavation. The excavator rerouted the excavation 373' away from the original planned excavation route, that was previously marked by cenex pipeline and hydro excavated at the planned crossing location, in coordination with the excavator. The reroute location was within view of the existing cenex pipeline markings at the planned excavation location. Upon deciding to reroute the excavation, the excavator failed to contact nd one call to request a new locate nor did they contact cenex pipeline to provide notification of the change in route. 1353 tons of contaminated soil were transported to ihd solids management, llc - williston, nd for disposal.
Detailed record list
Report Received Date
2013-08-07 00:00:00
Iyear
2013
Report Number
20130269
Supplemental Number
18656
Report Type
Supplemental Final
Operator Id
2170
Name
Cenex Pipeline Llc
Operator Street Address
803 Hwy 212 S (Po Box 909)
Operator City Name
Laurel
Operator State Abbreviation
MT
Operator Postal Code
59044
Local Datetime
2013-07-09 15:02:00
Location Latitude
47.7826
Location Longitude
-103.56694
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Gasoline (Non-Ethanol)
Unintentional Release Bbls
870
Recovered Bbls
820
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime
2013-07-09 15:02:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-07-09 15:05:00
Restart Datetime
2013-07-12 17:45:00
On Site Datetime
2013-07-09 17:15:00
Nrc Rpt Datetime
2013-07-09 15:28:00
Nrc Rpt Num
1053247
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Automatic
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
0
Pipe Fac Name
Glendive To Minot 8"
Segment Name
Glendive To Minot 8"
Onshore State Abbreviation
Nd
Onshore Postal Code
58835
Onshore City Name
Nearest City Was Arnegard, Nd
Onshore County Name
Mckenzie
Designated Location
Milepost/valve Station
Designated Name
81
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Excavation
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8.625
Pipe Wall Thickness
0.188
Pipe Smys
46000
Pipe Specification
Api 5l X46
Pipe Seam Type
Erw - Low Frequency
Pipe Manufacturer
Cal-Metal
Pipe Coating Type
Coal Tar
Installation Year
1960
Manufactured Year
1960
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
7
Puncture Circum
9
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Vegetation Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
No
Est Cost Oper Paid
15000
Est Cost Gas Released
110000
Est Cost Prop Damage
30000
Est Cost Emergency
150000
Est Cost Environmental
220000
Est Cost Other
50000
Est Cost Other Details
Continued Monitoring.
Prpty
575000
Accident Psig
500
Mop Psig
1135
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
453244
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind
Yes
Invest No Schedule Ind Details
It Was Determined That Controller Action Did Not Contribute To This Incident. The Controller Followed Procedures And Responded Appropriately And Promptly To The Incident, Therefore There Was No Cause To Further Investigate Fatigue.
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
Notify Cga Dirt
Yes
Private Row Ind
Yes
Private Subtype
Private Landowner
Excavator Type
Contractor
Excavator Equipment
Backhoe/trackhoe
Work Performed
Water
One Call Notified Ind
Yes
One Call Ticket Num
13093161
Locator Type
Utility Owner
Visible Marks
Yes
Service Interruption
Yes
Service Interruption Hours
75
Root Cause Category
Notification Issue
Root Cause Type
No Notification Made To The One-Call Center/811
Preparer Name
M******* S*****
Preparer Title
Dot Compliance Coordinator
Preparer Email
M**************@c*****.com
Preparer Telephone
406-628-5293
Preparer Fax
406-628-5390
Prepared Date
2013-10-24 00:00:00
Authorizer Name
J*** T******
Authorizer Telephone
406-628-5200
Authorizer Title
President Cenex Pipeline
Authorizer Email
J***********@c*****.com
Narrative
On july 9, 2013, cenex pipeline was delivering product into the glendive terminal with the balance pumping to minot, nd at a rate of approximately 1100 barrels per hour. At approximately 3:02 p.M. Mdt, the cenex pipeline controller noticed a significant pressure drop at the discharge of glendive terminal and arnegard station. The controller began to shut down the 8 inch diameter pipeline segment between glendive and minot as a result of an unexplained pressure drop and had the pipeline shutdown and rov's closed by 3:05 and 25 seconds. At approximately 3:11 p.M., a representative of the excavator phoned the control center to report that their company may have hit the pipeline during excavation and believe that it is damaged. The excavator reported the approximate location of the release in the area between alexander and arnegard in section 26 and 27. The puncture occurred near cenex pipeline mile post 81, and a photograph of the damaged pipe is included in exhibit section 7. Cenex pipeline estimates that 870 barrels of gasoline was released at the site with approximately 38 barrels of free product being recovered. The released product did not ignite, did not reach any surface water, and there were no reported injuries or fatalities as a result of this release. The cause of this damage was determined to be excavator failure to notify the one call center of a change in location of the excavation. The excavator rerouted the excavation 373' away from the original planned excavation route, that was previously marked by cenex pipeline and hydro excavated at the planned crossing location, in coordination with the excavator. The reroute location was within view of the existing cenex pipeline markings at the planned excavation location. Upon deciding to reroute the excavation, the excavator failed to contact nd one call to request a new locate nor did they contact cenex pipeline to provide notification of the change in route. 1353 tons of contaminated soil were transported to ihd solids management, llc - williston, nd for disposal.
| Report Received Date | 2013-08-07 00:00:00 |
|---|---|
| Iyear | 2013 |
| Report Number | 20130269 |
| Supplemental Number | 18656 |
| Report Type | Supplemental Final |
| Operator Id | 2170 PHMSA Enforcement |
| Name | Cenex Pipeline Llc |
| Operator Street Address | 803 Hwy 212 S (Po Box 909) |
| Operator City Name | Laurel |
| Operator State Abbreviation | MT |
| Operator Postal Code | 59044 |
| Local Datetime | 2013-07-09 15:02:00 |
| Location Latitude | 47.7826 Google Maps OpenStreetMap |
| Location Longitude | -103.56694 Google Maps OpenStreetMap |
| Commodity Released Type | Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions |
| Commodity Subtype | Gasoline (Non-Ethanol) |
| Unintentional Release Bbls | 870 |
| Recovered Bbls | 820 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations) |
| Incident Identified Datetime | 2013-07-09 15:02:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2013-07-09 15:05:00 |
| Restart Datetime | 2013-07-12 17:45:00 |
| On Site Datetime | 2013-07-09 17:15:00 |
| Nrc Rpt Datetime | 2013-07-09 15:28:00 |
| Nrc Rpt Num | 1053247 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Automatic |
| Downstream Valve Type Ind | Automatic |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Glendive To Minot 8" |
| Segment Name | Glendive To Minot 8" |
| Onshore State Abbreviation | Nd |
| Onshore Postal Code | 58835 |
| Onshore City Name | Nearest City Was Arnegard, Nd |
| Onshore County Name | Mckenzie |
| Designated Location | Milepost/valve Station |
| Designated Name | 81 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Exposed Due To Excavation |
| Depth Of Cover | 48 |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 8.625 |
| Pipe Wall Thickness | 0.188 |
| Pipe Smys | 46000 |
| Pipe Specification | Api 5l X46 |
| Pipe Seam Type | Erw - Low Frequency |
| Pipe Manufacturer | Cal-Metal |
| Pipe Coating Type | Coal Tar |
| Installation Year | 1960 |
| Manufactured Year | 1960 |
| Material Involved | Carbon Steel |
| Release Type | Mechanical Puncture |
| Puncture Axial | 7 |
| Puncture Circum | 9 |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Vegetation Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 15000 |
| Est Cost Gas Released | 110000 |
| Est Cost Prop Damage | 30000 |
| Est Cost Emergency | 150000 |
| Est Cost Environmental | 220000 |
| Est Cost Other | 50000 |
| Est Cost Other Details | Continued Monitoring. |
| Prpty | 575000 |
| Accident Psig | 500 |
| Mop Psig | 1135 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 453244 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest No Schedule Ind | Yes |
| Invest No Schedule Ind Details | It Was Determined That Controller Action Did Not Contribute To This Incident. The Controller Followed Procedures And Responded Appropriately And Promptly To The Incident, Therefore There Was No Cause To Further Investigate Fatigue. |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Excavation Damage |
| Cause Details | Excavation Damage By Third Party |
| Ex Party Type | Excavation Damage By Third Party |
| Prior Notification Ind | Yes |
| One Call System Ind | Yes |
| Notify Cga Dirt | Yes |
| Private Row Ind | Yes |
| Private Subtype | Private Landowner |
| Excavator Type | Contractor |
| Excavator Equipment | Backhoe/trackhoe |
| Work Performed | Water |
| One Call Notified Ind | Yes |
| One Call Ticket Num | 13093161 |
| Locator Type | Utility Owner |
| Visible Marks | Yes |
| Service Interruption | Yes |
| Service Interruption Hours | 75 |
| Root Cause Category | Notification Issue |
| Root Cause Type | No Notification Made To The One-Call Center/811 |
| Preparer Name | M******* S***** |
| Preparer Title | Dot Compliance Coordinator |
| Preparer Email | M**************@c*****.com |
| Preparer Telephone | 406-628-5293 |
| Preparer Fax | 406-628-5390 |
| Prepared Date | 2013-10-24 00:00:00 |
| Authorizer Name | J*** T****** |
| Authorizer Telephone | 406-628-5200 |
| Authorizer Title | President Cenex Pipeline |
| Authorizer Email | J***********@c*****.com |
| Narrative | On july 9, 2013, cenex pipeline was delivering product into the glendive terminal with the balance pumping to minot, nd at a rate of approximately 1100 barrels per hour. At approximately 3:02 p.M. Mdt, the cenex pipeline controller noticed a significant pressure drop at the discharge of glendive terminal and arnegard station. The controller began to shut down the 8 inch diameter pipeline segment between glendive and minot as a result of an unexplained pressure drop and had the pipeline shutdown and rov's closed by 3:05 and 25 seconds. At approximately 3:11 p.M., a representative of the excavator phoned the control center to report that their company may have hit the pipeline during excavation and believe that it is damaged. The excavator reported the approximate location of the release in the area between alexander and arnegard in section 26 and 27. The puncture occurred near cenex pipeline mile post 81, and a photograph of the damaged pipe is included in exhibit section 7. Cenex pipeline estimates that 870 barrels of gasoline was released at the site with approximately 38 barrels of free product being recovered. The released product did not ignite, did not reach any surface water, and there were no reported injuries or fatalities as a result of this release. The cause of this damage was determined to be excavator failure to notify the one call center of a change in location of the excavation. The excavator rerouted the excavation 373' away from the original planned excavation route, that was previously marked by cenex pipeline and hydro excavated at the planned crossing location, in coordination with the excavator. The reroute location was within view of the existing cenex pipeline markings at the planned excavation location. Upon deciding to reroute the excavation, the excavator failed to contact nd one call to request a new locate nor did they contact cenex pipeline to provide notification of the change in route. 1353 tons of contaminated soil were transported to ihd solids management, llc - williston, nd for disposal. |
External Resources
PHMSA pipeline safety insights.
Product
Features
Company
All rights reserved. Copyright © by ClearPHMSA