HL incident on 2013-04-06 — TX

Operator
Mccain Pipeline Company
Cause
Miscellaneous Root Causes
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$20,000
Incident datetime
2013-04-06 17:00
Report number
Location
TX
Narrative
On april 6, 2013, during the patrol of our pipeline right of way, we discovered a jet fuel leak. After removing the coating from, and inspecting the 6-inch pipeline at the leak location, we discovered a dent and a pinhole within the dent. Based on the dent location, we determined the line had been mechanically damaged most likely during the widening of highway 45 many years earlier. As a short-term pipe repair, we installed a 4-inch clamp; as a permanent repair, we removed and replaced an approximately 60-foot segment of the pipeline, and installed a new 300# ansi valve and flange. The pipeline was pressured tested on may 19, 2013, and was returned to service following the successful pressure test. Ops southern region was notified of the event on april 7, 2013 and on may 17, 2013, approved mccain pipeline company's plan for returning the pipeline to service. Approximately 364.11 tons of impacted soil was removed and properly disposed at the pine ridge landfill located in meridian, mississippi. The area excavated was completely backfilled. The initial response is completed and confirmatory sampling has determined that there are no remaining environmental impacts.
Detailed record list
Report Received Date
2013-07-26 00:00:00
Iyear
2013
Report Number
20130255
Supplemental Number
20666
Report Type
Supplemental Final
Operator Id
Name
Mccain Pipeline Company
Operator Street Address
4635 Southwest Freeway, Suite 910
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77027
Local Datetime
2013-04-06 17:00:00
Location Latitude
Location Longitude
-88.56550277
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls
1
Recovered Bbls
1
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Ground Patrol By Operator Or Its Contractor
Operator Type
Operator Employee
Incident Identified Datetime
2013-04-06 17:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-04-06 17:00:00
Restart Datetime
2013-05-19 17:00:00
On Site Datetime
2013-04-06 18:30:00
Nrc Rpt Datetime
2013-04-06 17:10:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Mccain Pipeline Company
Segment Name
East Side Of Highway 45
Onshore State Abbreviation
Ms
Onshore Postal Code
39342
Onshore City Name
Lockhart
Onshore County Name
Lauderdale
Designated Location
Milepost/valve Station
Designated Name
W. Of Hwy 45
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
36
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Seam
Pipe Diameter
4
Pipe Wall Thickness
0.133
Pipe Smys
24000
Pipe Specification
Schedule 40
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Unknown
Pipe Coating Type
Coal Tar
Installation Year
1961
Manufactured Year
1961
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
0.1
Puncture Circum
0.1
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
142
Est Cost Prop Damage
20000
Est Cost Emergency
80000
Est Cost Environmental
50000
Est Cost Other
0
Prpty
150142
Accident Psig
150
Mop Psig
250
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
21120
Internal Inspection Ind
No
Tight Mitered Ind
Yes
Operation Complications Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Previous Damage Due To Excavation Activity
Ex Party Type
Previous Damage Due To Excavation Activity
Notify Cga Dirt
No
Public Row Ind
Yes
Public Subtype
State Highway
Excavator Type
Unknown/other
Excavator Equipment
Unknown/other
Work Performed
Road Work
One Call Notified Ind
No
Locator Type
Data Not Collected
Visible Marks
Data Not Collected
Service Interruption
No
Root Cause Category
Miscellaneous Root Causes
Root Cause Type
Previous Damage
Collected Data Ind
No
Insp Compl Before Damage Ind
No
Has Hydrtst Conduc Before Ind
Yes
Hydrtst Most Rcnt Year
1990
Hydrtst Most Rcnt Pressure
350
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
M*** R****
Preparer Title
President Of Ptmc
Preparer Email
M****@p***.us
Preparer Telephone
713-627-1700
Preparer Fax
713-621-9292
Prepared Date
2015-08-14 00:00:00
Authorizer Name
M*** R****
Authorizer Telephone
713-627-1700
Authorizer Title
President Of Ptmc
Authorizer Email
M****@p***.us
Narrative
On april 6, 2013, during the patrol of our pipeline right of way, we discovered a jet fuel leak. After removing the coating from, and inspecting the 6-inch pipeline at the leak location, we discovered a dent and a pinhole within the dent. Based on the dent location, we determined the line had been mechanically damaged most likely during the widening of highway 45 many years earlier. As a short-term pipe repair, we installed a 4-inch clamp; as a permanent repair, we removed and replaced an approximately 60-foot segment of the pipeline, and installed a new 300# ansi valve and flange. The pipeline was pressured tested on may 19, 2013, and was returned to service following the successful pressure test. Ops southern region was notified of the event on april 7, 2013 and on may 17, 2013, approved mccain pipeline company's plan for returning the pipeline to service. Approximately 364.11 tons of impacted soil was removed and properly disposed at the pine ridge landfill located in meridian, mississippi. The area excavated was completely backfilled. The initial response is completed and confirmatory sampling has determined that there are no remaining environmental impacts.
Report Received Date 2013-07-26 00:00:00
Iyear 2013
Report Number 20130255
Supplemental Number 20666
Report Type Supplemental Final
Operator Id 32174 PHMSA Enforcement
Name Mccain Pipeline Company
Operator Street Address 4635 Southwest Freeway, Suite 910
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77027
Local Datetime 2013-04-06 17:00:00
Location Latitude 32.5007778 Google Maps OpenStreetMap
Location Longitude -88.56550277 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls 1
Recovered Bbls 1
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Ground Patrol By Operator Or Its Contractor
Operator Type Operator Employee
Incident Identified Datetime 2013-04-06 17:00:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2013-04-06 17:00:00
Restart Datetime 2013-05-19 17:00:00
On Site Datetime 2013-04-06 18:30:00
Nrc Rpt Datetime 2013-04-06 17:10:00
Nrc Rpt Num 1043156 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name Mccain Pipeline Company
Segment Name East Side Of Highway 45
Onshore State Abbreviation Ms
Onshore Postal Code 39342
Onshore City Name Lockhart
Onshore County Name Lauderdale
Designated Location Milepost/valve Station
Designated Name W. Of Hwy 45
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 36
Crossing No
Pipe Facility Type Intrastate
Item Involved Pipe
Pipe Type Pipe Seam
Pipe Diameter 4
Pipe Wall Thickness 0.133
Pipe Smys 24000
Pipe Specification Schedule 40
Pipe Seam Type Erw - High Frequency
Pipe Manufacturer Unknown
Pipe Coating Type Coal Tar
Installation Year 1961
Manufactured Year 1961
Material Involved Carbon Steel
Release Type Mechanical Puncture
Puncture Axial 0.1
Puncture Circum 0.1
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment Yes
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 142
Est Cost Prop Damage 20000
Est Cost Emergency 80000
Est Cost Environmental 50000
Est Cost Other 0
Prpty 150142
Accident Psig 150
Mop Psig 250
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 21120
Internal Inspection Ind No
Tight Mitered Ind Yes
Operation Complications Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Previous Damage Due To Excavation Activity
Ex Party Type Previous Damage Due To Excavation Activity
Notify Cga Dirt No
Public Row Ind Yes
Public Subtype State Highway
Excavator Type Unknown/other
Excavator Equipment Unknown/other
Work Performed Road Work
One Call Notified Ind No
Locator Type Data Not Collected
Visible Marks Data Not Collected
Service Interruption No
Root Cause Category Miscellaneous Root Causes
Root Cause Type Previous Damage
Collected Data Ind No
Insp Compl Before Damage Ind No
Has Hydrtst Conduc Before Ind Yes
Hydrtst Most Rcnt Year 1990
Hydrtst Most Rcnt Pressure 350
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Preparer Name M*** R****
Preparer Title President Of Ptmc
Preparer Email M****@p***.us
Preparer Telephone 713-627-1700
Preparer Fax 713-621-9292
Prepared Date 2015-08-14 00:00:00
Authorizer Name M*** R****
Authorizer Telephone 713-627-1700
Authorizer Title President Of Ptmc
Authorizer Email M****@p***.us
Narrative On april 6, 2013, during the patrol of our pipeline right of way, we discovered a jet fuel leak. After removing the coating from, and inspecting the 6-inch pipeline at the leak location, we discovered a dent and a pinhole within the dent. Based on the dent location, we determined the line had been mechanically damaged most likely during the widening of highway 45 many years earlier. As a short-term pipe repair, we installed a 4-inch clamp; as a permanent repair, we removed and replaced an approximately 60-foot segment of the pipeline, and installed a new 300# ansi valve and flange. The pipeline was pressured tested on may 19, 2013, and was returned to service following the successful pressure test. Ops southern region was notified of the event on april 7, 2013 and on may 17, 2013, approved mccain pipeline company's plan for returning the pipeline to service. Approximately 364.11 tons of impacted soil was removed and properly disposed at the pine ridge landfill located in meridian, mississippi. The area excavated was completely backfilled. The initial response is completed and confirmatory sampling has determined that there are no remaining environmental impacts.