HL incident on 2013-06-05 — TX
Operator
Enbridge Energy, Limited Partnership
Cause
Equipment Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$1,000
Incident datetime
2013-06-05 08:38
Report number
Location
TX
Narrative
On june 5 at 08:38 local time, the edmonton control center experienced a gas alarm on unit 5.2 at the mackinaw city station. Onsite plm personnel were notified to investigate alarm. The line was down at the time due to a normal operating shutdown at the superior terminal for pigging on line 5. It was discovered that a 3/4" nipple on the unit had cracked due to normal wear and tear. At the time of the incident ngl was across the station. The unit was isolated and the line was restarted at a reduced pressure and operated until crude oil was across the station to facilitate repair. Once crude had crossed the station later that day, the unit was flushed, drained and the cracked 3/4" nipple on the unit was replaced. Approximately 15 yards of soil has been disposed of at an approved landfill due to odor not saturated with product.
Detailed record list
Report Received Date
2013-07-02 00:00:00
Iyear
2013
Report Number
20130238
Supplemental Number
18870
Report Type
Supplemental Final
Operator Id
11169
Name
Enbridge Energy, Limited Partnership
Operator Street Address
915 N Eldridge Parkway, Suite 1100
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77079
Local Datetime
2013-06-05 08:38:00
Location Latitude
45.78611
Location Longitude
-84.77444
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls
0.48
Intentional Release Bbls
0
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Incident Identified Datetime
2013-06-05 08:38:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Pipeline Was Already Shut Down For Pigging On Line 5 At Superior Terminal
On Site Datetime
2013-06-05 08:38:00
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Line 5
Segment Name
Line 5 Mackinaw Station
Onshore State Abbreviation
Mi
Onshore Postal Code
49701
Onshore City Name
Mackinaw City
Onshore County Name
Emmet
Designated Location
Milepost/valve Station
Designated Name
1479mp
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Pipe Facility Type
Interstate
Item Involved
Pump
Release Type
Leak
Leak Type
Connection Failure
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Commercially Nav Ind
Yes
Commercially Nav Yes No
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
20
Est Cost Prop Damage
1000
Est Cost Emergency
3000
Est Cost Environmental
7000
Est Cost Other
0
Prpty
11020
Pipeline Function
> 20% Smys Regulated Transmission
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Threaded Connection/coupling Failure
Eq Failure Type
Threaded Connection/coupling Failure
Preparer Name
S**** S****
Preparer Title
Compliance Analyst
Preparer Email
S**********@e*******.com
Preparer Telephone
218-464-5754
Preparer Fax
218-464-5992
Prepared Date
2013-12-19 00:00:00
Authorizer Name
D**** S*******
Authorizer Telephone
218-464-5751
Authorizer Title
Manager Us Pipeline Compliance
Authorizer Email
D*************@e*******.com
Narrative
On june 5 at 08:38 local time, the edmonton control center experienced a gas alarm on unit 5.2 at the mackinaw city station. Onsite plm personnel were notified to investigate alarm. The line was down at the time due to a normal operating shutdown at the superior terminal for pigging on line 5. It was discovered that a 3/4" nipple on the unit had cracked due to normal wear and tear. At the time of the incident ngl was across the station. The unit was isolated and the line was restarted at a reduced pressure and operated until crude oil was across the station to facilitate repair. Once crude had crossed the station later that day, the unit was flushed, drained and the cracked 3/4" nipple on the unit was replaced. Approximately 15 yards of soil has been disposed of at an approved landfill due to odor not saturated with product.
| Report Received Date | 2013-07-02 00:00:00 |
|---|---|
| Iyear | 2013 |
| Report Number | 20130238 |
| Supplemental Number | 18870 |
| Report Type | Supplemental Final |
| Operator Id | 11169 PHMSA Enforcement |
| Name | Enbridge Energy, Limited Partnership |
| Operator Street Address | 915 N Eldridge Parkway, Suite 1100 |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77079 |
| Local Datetime | 2013-06-05 08:38:00 |
| Location Latitude | 45.78611 Google Maps OpenStreetMap |
| Location Longitude | -84.77444 Google Maps OpenStreetMap |
| Commodity Released Type | Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions |
| Commodity Subtype | Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid) |
| Unintentional Release Bbls | 0.48 |
| Intentional Release Bbls | 0 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Incident Identified Datetime | 2013-06-05 08:38:00 |
| System Part Involved | Onshore Pump/meter Station Equipment And Piping |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | The Pipeline Was Already Shut Down For Pigging On Line 5 At Superior Terminal |
| On Site Datetime | 2013-06-05 08:38:00 |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Line 5 |
| Segment Name | Line 5 Mackinaw Station |
| Onshore State Abbreviation | Mi |
| Onshore Postal Code | 49701 |
| Onshore City Name | Mackinaw City |
| Onshore County Name | Emmet |
| Designated Location | Milepost/valve Station |
| Designated Name | 1479mp |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Pipe Facility Type | Interstate |
| Item Involved | Pump |
| Release Type | Leak |
| Leak Type | Connection Failure |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| Commercially Nav Ind | Yes |
| Commercially Nav Yes No | Yes |
| Other Pop Ind | Yes |
| Other Pop Yes No | Yes |
| Usa Ecological Ind | Yes |
| Usa Ecological Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 20 |
| Est Cost Prop Damage | 1000 |
| Est Cost Emergency | 3000 |
| Est Cost Environmental | 7000 |
| Est Cost Other | 0 |
| Prpty | 11020 |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Threaded Connection/coupling Failure |
| Eq Failure Type | Threaded Connection/coupling Failure |
| Preparer Name | S**** S**** |
| Preparer Title | Compliance Analyst |
| Preparer Email | S**********@e*******.com |
| Preparer Telephone | 218-464-5754 |
| Preparer Fax | 218-464-5992 |
| Prepared Date | 2013-12-19 00:00:00 |
| Authorizer Name | D**** S******* |
| Authorizer Telephone | 218-464-5751 |
| Authorizer Title | Manager Us Pipeline Compliance |
| Authorizer Email | D*************@e*******.com |
| Narrative | On june 5 at 08:38 local time, the edmonton control center experienced a gas alarm on unit 5.2 at the mackinaw city station. Onsite plm personnel were notified to investigate alarm. The line was down at the time due to a normal operating shutdown at the superior terminal for pigging on line 5. It was discovered that a 3/4" nipple on the unit had cracked due to normal wear and tear. At the time of the incident ngl was across the station. The unit was isolated and the line was restarted at a reduced pressure and operated until crude oil was across the station to facilitate repair. Once crude had crossed the station later that day, the unit was flushed, drained and the cracked 3/4" nipple on the unit was replaced. Approximately 15 yards of soil has been disposed of at an approved landfill due to odor not saturated with product. |
External Resources
PHMSA pipeline safety insights.
Product
Features
Company
All rights reserved. Copyright © by ClearPHMSA