Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2013-05-18 — OK
Operator
Magellan Ammonia Pipeline, L.p.
Cause
Material Failure Of Pipe Or Weld
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$12,049
Incident datetime
2013-05-18 12:54
Report number
Location
OK
Narrative
A third party individual hunting mushrooms identified a dead sport of vegetation and notified the magellan operations control center. The line was immediately shut down and an investigation was initiated. A pinhole size anomaly in a girth weld was subsequently discovered. The line was repaired by installing a type b full encirclement pressure containing sleeve and the pipe repair was coated. Impacted soil was remediated in accordance with company and state standards. Note: when the release was initially discovered, indications were that approximately only 4 gallons of product had been released, which is below the minimum release reporting threshold in 49 cfr part 195.50. However, during the ongoing investigation and repair of the release it was later determined on may 21, (3 days after the initial discovery of the release) that perhaps as many as 100 gallons of product may have been released. At that point in time, the decision was made to notify the national response center that the release had occurred, which accounts for the lapse of time noted in part a of this report between the occurrence of the release and the phone call to the nrc. However, the notification to the nrc was made to comply with environmental regulations when it was determined that the estimated volume of anhydrous ammonia released may have hit or exceeded the minimum reporting threshold in applicable environmental regulations. The character and nature of the release was not considered to be significant within the context of part 195.52, which also requires notifying the national response center. Magellan does not think the delay in contacting the nrc constitutes a breach of part 195 reporting requirements, since the nature of the release did not warrant calling the nrc under part 195. In filing this updated final report, the revised total cost now exceeds $50,000, which meets PHMSA filing requirements for a "large" spill.
Detailed record list
Report Received Date
2013-06-15 00:00:00
Iyear
2013
Report Number
20130210
Supplemental Number
19957
Report Type
Supplemental Final
Operator Id
12105
Name
Magellan Ammonia Pipeline, L.p.
Operator Street Address
One Williams Center, Otc-9 P.o. Box 22186
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74172
Local Datetime
2013-05-18 12:54:00
Location Latitude
41.90877
Location Longitude
-96.24902
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Anhydrous Ammonia
Unintentional Release Bbls
2.39
Intentional Release Bbls
0.01
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2013-05-18 12:54:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-05-18 12:54:00
Restart Datetime
2013-05-20 15:47:00
On Site Datetime
2013-05-18 12:54:00
Nrc Rpt Datetime
2013-05-21 21:34:00
Nrc Rpt Num
1047900
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Remotely Controlled
Pipe Fac Name
Valley To Whiting Line Segment
Segment Name
Line Id#502 (West Leg)
Onshore State Abbreviation
Ne
Onshore Postal Code
68020
Onshore City Name
Decatur
Onshore County Name
Burt
Designated Location
Milepost/valve Station
Designated Name
262.78
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Weld, Including Heat-Affected Zone
Pipe Diameter
8.625
Pipe Wall Thickness
0.156
Pipe Smys
46000
Pipe Specification
Api 5lx-46
Pipe Seam Type
Erw - Low Frequency
Pipe Manufacturer
Lone Star
Pipe Coating Type
Cold Applied Tape
Weld Subtype
Pipe Girth Weld
Installation Year
1968
Manufactured Year
1968
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
195
Est Cost Prop Damage
12049
Est Cost Emergency
10500
Est Cost Environmental
27376
Est Cost Other
0
Prpty
50120
Accident Psig
471
Mop Psig
1198
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
269280
Internal Inspection Ind
Yes
Operation Complications Ind
Yes
Incompat Commod Ind
Yes
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Since the release was from a pinhole in a girth weld, it was determined that neither the control room nor the controller on duty caused or contributed to the release.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Material Failure Of Pipe Or Weld
Cause Details
Design-, Construction-, Installation-, Or Fabrication-Related
Field Exam Ind
Yes
Failure Type
Design-, Construction-, Installation-, Or Fabrication-Related
Other Factor
Yes
Other Factor Details
Pinhole In Girth Weld
Pwf Additional Other Ind
Yes
Collected Data Ind
Yes
Axial Magnetic Flx Lkg Ind
Yes
Geometry Deformation Ind
Yes
Axial Recent Year
2006
Geometry Recent Year
2004
Has Hydrtst Conduc Before Ind
Yes
Hydrtst Most Rcnt Year
2010
Hydrtst Most Rcnt Pressure
1520
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
K****** L* L*******
Preparer Title
Sr. Compliance Coordinator
Preparer Email
K***********@m*********.com
Preparer Telephone
918-574-7315
Preparer Fax
918-574-7377
Prepared Date
2014-12-11 00:00:00
Authorizer Name
K****** L* L*******
Authorizer Telephone
918-574-7315
Authorizer Title
Sr. Compliance Coordinator
Authorizer Email
K***********@m*********.com
Narrative
A third party individual hunting mushrooms identified a dead sport of vegetation and notified the magellan operations control center. The line was immediately shut down and an investigation was initiated. A pinhole size anomaly in a girth weld was subsequently discovered. The line was repaired by installing a type b full encirclement pressure containing sleeve and the pipe repair was coated. Impacted soil was remediated in accordance with company and state standards. Note: when the release was initially discovered, indications were that approximately only 4 gallons of product had been released, which is below the minimum release reporting threshold in 49 cfr part 195.50. However, during the ongoing investigation and repair of the release it was later determined on may 21, (3 days after the initial discovery of the release) that perhaps as many as 100 gallons of product may have been released. At that point in time, the decision was made to notify the national response center that the release had occurred, which accounts for the lapse of time noted in part a of this report between the occurrence of the release and the phone call to the nrc. However, the notification to the nrc was made to comply with environmental regulations when it was determined that the estimated volume of anhydrous ammonia released may have hit or exceeded the minimum reporting threshold in applicable environmental regulations. The character and nature of the release was not considered to be significant within the context of part 195.52, which also requires notifying the national response center. Magellan does not think the delay in contacting the nrc constitutes a breach of part 195 reporting requirements, since the nature of the release did not warrant calling the nrc under part 195. In filing this updated final report, the revised total cost now exceeds $50,000, which meets PHMSA filing requirements for a "large" spill.
| Report Received Date | 2013-06-15 00:00:00 |
|---|---|
| Iyear | 2013 |
| Report Number | 20130210 |
| Supplemental Number | 19957 |
| Report Type | Supplemental Final |
| Operator Id | 12105 PHMSA Enforcement |
| Name | Magellan Ammonia Pipeline, L.p. |
| Operator Street Address | One Williams Center, Otc-9 P.o. Box 22186 |
| Operator City Name | Tulsa |
| Operator State Abbreviation | OK |
| Operator Postal Code | 74172 |
| Local Datetime | 2013-05-18 12:54:00 |
| Location Latitude | 41.90877 Google Maps OpenStreetMap |
| Location Longitude | -96.24902 Google Maps OpenStreetMap |
| Commodity Released Type | Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions |
| Commodity Subtype | Anhydrous Ammonia |
| Unintentional Release Bbls | 2.39 |
| Intentional Release Bbls | 0.01 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Notification From Public |
| Incident Identified Datetime | 2013-05-18 12:54:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2013-05-18 12:54:00 |
| Restart Datetime | 2013-05-20 15:47:00 |
| On Site Datetime | 2013-05-18 12:54:00 |
| Nrc Rpt Datetime | 2013-05-21 21:34:00 |
| Nrc Rpt Num | 1047900 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Remotely Controlled |
| Downstream Valve Type Ind | Remotely Controlled |
| Pipe Fac Name | Valley To Whiting Line Segment |
| Segment Name | Line Id#502 (West Leg) |
| Onshore State Abbreviation | Ne |
| Onshore Postal Code | 68020 |
| Onshore City Name | Decatur |
| Onshore County Name | Burt |
| Designated Location | Milepost/valve Station |
| Designated Name | 262.78 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Weld, Including Heat-Affected Zone |
| Pipe Diameter | 8.625 |
| Pipe Wall Thickness | 0.156 |
| Pipe Smys | 46000 |
| Pipe Specification | Api 5lx-46 |
| Pipe Seam Type | Erw - Low Frequency |
| Pipe Manufacturer | Lone Star |
| Pipe Coating Type | Cold Applied Tape |
| Weld Subtype | Pipe Girth Weld |
| Installation Year | 1968 |
| Manufactured Year | 1968 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | Yes |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 195 |
| Est Cost Prop Damage | 12049 |
| Est Cost Emergency | 10500 |
| Est Cost Environmental | 27376 |
| Est Cost Other | 0 |
| Prpty | 50120 |
| Accident Psig | 471 |
| Mop Psig | 1198 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 269280 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | Yes |
| Incompat Commod Ind | Yes |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Since the release was from a pinhole in a girth weld, it was determined that neither the control room nor the controller on duty caused or contributed to the release. |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Material Failure Of Pipe Or Weld |
| Cause Details | Design-, Construction-, Installation-, Or Fabrication-Related |
| Field Exam Ind | Yes |
| Failure Type | Design-, Construction-, Installation-, Or Fabrication-Related |
| Other Factor | Yes |
| Other Factor Details | Pinhole In Girth Weld |
| Pwf Additional Other Ind | Yes |
| Collected Data Ind | Yes |
| Axial Magnetic Flx Lkg Ind | Yes |
| Geometry Deformation Ind | Yes |
| Axial Recent Year | 2006 |
| Geometry Recent Year | 2004 |
| Has Hydrtst Conduc Before Ind | Yes |
| Hydrtst Most Rcnt Year | 2010 |
| Hydrtst Most Rcnt Pressure | 1520 |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | No |
| Preparer Name | K****** L* L******* |
| Preparer Title | Sr. Compliance Coordinator |
| Preparer Email | K***********@m*********.com |
| Preparer Telephone | 918-574-7315 |
| Preparer Fax | 918-574-7377 |
| Prepared Date | 2014-12-11 00:00:00 |
| Authorizer Name | K****** L* L******* |
| Authorizer Telephone | 918-574-7315 |
| Authorizer Title | Sr. Compliance Coordinator |
| Authorizer Email | K***********@m*********.com |
| Narrative | A third party individual hunting mushrooms identified a dead sport of vegetation and notified the magellan operations control center. The line was immediately shut down and an investigation was initiated. A pinhole size anomaly in a girth weld was subsequently discovered. The line was repaired by installing a type b full encirclement pressure containing sleeve and the pipe repair was coated. Impacted soil was remediated in accordance with company and state standards. Note: when the release was initially discovered, indications were that approximately only 4 gallons of product had been released, which is below the minimum release reporting threshold in 49 cfr part 195.50. However, during the ongoing investigation and repair of the release it was later determined on may 21, (3 days after the initial discovery of the release) that perhaps as many as 100 gallons of product may have been released. At that point in time, the decision was made to notify the national response center that the release had occurred, which accounts for the lapse of time noted in part a of this report between the occurrence of the release and the phone call to the nrc. However, the notification to the nrc was made to comply with environmental regulations when it was determined that the estimated volume of anhydrous ammonia released may have hit or exceeded the minimum reporting threshold in applicable environmental regulations. The character and nature of the release was not considered to be significant within the context of part 195.52, which also requires notifying the national response center. Magellan does not think the delay in contacting the nrc constitutes a breach of part 195 reporting requirements, since the nature of the release did not warrant calling the nrc under part 195. In filing this updated final report, the revised total cost now exceeds $50,000, which meets PHMSA filing requirements for a "large" spill. |