HL incident on 2013-05-15 — TX

Operator
Enterprise Products Operating Llc
Cause
Equipment Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$15,000
Incident datetime
2013-05-15 11:49
Report number
Location
TX
Narrative
At 08:20 on 5/15/13, a third party operator reported a leak on a valve bonnet at the manual block valve site (milepost 62.5) near levelland, texas. A technician was dispatched and arrived onsite at 09:47. Upon arrival, the technician noticed a minor leak on the valve and attempted to repair the leak. However, the leak could not be stopped and the line was shut-down and blocked in at 10:55. Note: the particular valve in question was not blocked initially. The pipeline was shut down by pipeline control at 1055 consistent with pl control protocol in an effort to reduce the pressure as attempts were made to re-pack the valve that was leaking. Line pressure @ 1055 was approximately 200 psi when repair attempts commenced. At 11:49 it was determined the leak had met the definition of an accident and the estimated cost to repair the leak would exceed $50,000 and the nrc was notified at 12:23 local time. At 08:00 on 5/16/2013, nitrogen inert was injected at levelland station for approximately 23 miles. The valve at milepost 62.5 was removed and replaced with a flanged type valve. The line was restarted at approximately 0035 5/17/2013.
Detailed record list
Report Received Date
2013-06-11 00:00:00
Iyear
2013
Report Number
20130204
Supplemental Number
18182
Report Type
Original Final
Operator Id
Name
Enterprise Products Operating Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2013-05-15 11:49:00
Location Latitude
Location Longitude
-102.4290155
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Other Hvl
Commodity Details
Propane
Unintentional Release Bbls
1
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Third Party Operator
Incident Identified Datetime
2013-05-15 11:49:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-05-15 11:49:00
Restart Datetime
2013-05-17 00:35:00
On Site Datetime
2013-05-15 11:49:00
Nrc Rpt Datetime
2013-05-15 12:23:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
South Leg Loop (Blue Line)
Segment Name
Lid 220
Onshore State Abbreviation
Tx
Onshore Postal Code
79336
Onshore City Name
Levelland
Onshore County Name
Hockley
Designated Location
Milepost/valve Station
Designated Name
62.5
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Valve
Valve Type
Mainline
Valve Mainline Type
Gate
Valve Manufacturer
M And J
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Seal Or Packing
Leak Type Other
Bonnet O-Ring
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
0
Est Cost Prop Damage
15000
Est Cost Emergency
51000
Est Cost Environmental
0
Est Cost Other
0
Prpty
66000
Accident Psig
300
Mop Psig
1295
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
124000
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Non-Threaded Connection Failure
Eq Failure Type
Non-Threaded Connection Failure
Other Non Threaded Ind
Seal (Not Pump Seal) Or Packing
Eq Additional Other Ind
Yes
Eq Additional Other Details
Dried Packing Due To Several Decades Of Service.
Preparer Name
N*** T*****
Preparer Title
Pipeline Compliance Engineer
Preparer Email
N*******@e****.com
Preparer Telephone
713-381-2493
Prepared Date
2013-06-11 00:00:00
Authorizer Name
N*** T*****
Authorizer Telephone
713-381-2493
Authorizer Title
Pipeline Compliance Engineer
Authorizer Email
N*******@e****.com
Narrative
A***********************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************@ 1055 was approximately 200 psi when repair attempts commenced. At 11:49 it was determined the leak had met the definition of an accident and the estimated cost to repair the leak would exceed $50,000 and the nrc was notified at 12:23 local time. At 08:00 on 5/16/2013, nitrogen inert was injected at levelland station for approximately 23 miles. The valve at milepost 62.5 was removed and replaced with a flanged type valve. *******************************************************.
Report Received Date 2013-06-11 00:00:00
Iyear 2013
Report Number 20130204
Supplemental Number 18182
Report Type Original Final
Operator Id 31618 PHMSA Enforcement
Name Enterprise Products Operating Llc
Operator Street Address 1100 Louisiana Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2013-05-15 11:49:00
Location Latitude 33.5890316 Google Maps OpenStreetMap
Location Longitude -102.4290155 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Other Hvl
Commodity Details Propane
Unintentional Release Bbls 1
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Other
Accident Details Third Party Operator
Incident Identified Datetime 2013-05-15 11:49:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2013-05-15 11:49:00
Restart Datetime 2013-05-17 00:35:00
On Site Datetime 2013-05-15 11:49:00
Nrc Rpt Datetime 2013-05-15 12:23:00
Nrc Rpt Num 1047225 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Remotely Controlled
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name South Leg Loop (Blue Line)
Segment Name Lid 220
Onshore State Abbreviation Tx
Onshore Postal Code 79336
Onshore City Name Levelland
Onshore County Name Hockley
Designated Location Milepost/valve Station
Designated Name 62.5
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Interstate
Item Involved Valve
Valve Type Mainline
Valve Mainline Type Gate
Valve Manufacturer M And J
Material Involved Carbon Steel
Release Type Leak
Leak Type Seal Or Packing
Leak Type Other Bonnet O-Ring
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 0
Est Cost Prop Damage 15000
Est Cost Emergency 51000
Est Cost Environmental 0
Est Cost Other 0
Prpty 66000
Accident Psig 300
Mop Psig 1295
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 124000
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind Yes
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Non-Threaded Connection Failure
Eq Failure Type Non-Threaded Connection Failure
Other Non Threaded Ind Seal (Not Pump Seal) Or Packing
Eq Additional Other Ind Yes
Eq Additional Other Details Dried Packing Due To Several Decades Of Service.
Preparer Name N*** T*****
Preparer Title Pipeline Compliance Engineer
Preparer Email N*******@e****.com
Preparer Telephone 713-381-2493
Prepared Date 2013-06-11 00:00:00
Authorizer Name N*** T*****
Authorizer Telephone 713-381-2493
Authorizer Title Pipeline Compliance Engineer
Authorizer Email N*******@e****.com
Narrative A***********************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************************@ 1055 was approximately 200 psi when repair attempts commenced. At 11:49 it was determined the leak had met the definition of an accident and the estimated cost to repair the leak would exceed $50,000 and the nrc was notified at 12:23 local time. At 08:00 on 5/16/2013, nitrogen inert was injected at levelland station for approximately 23 miles. The valve at milepost 62.5 was removed and replaced with a flanged type valve. *******************************************************.