HL incident on 2013-05-06 — TX

Operator
Shell Pipeline Co., L.p.
Cause
Excavation Issue
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$500
Incident datetime
2013-05-06 07:30
Report number
Location
TX
Narrative
Excavation was being performed around the suction line of the mainline pump station. There was asphalt in an area that needed to excavated. Used the backhoe to lift the asphalt. The backhoe bucket contacted the small diameter .75 inch pipe nipple and cracked the threads. The backhoe operator felt the contact and stopped. The pipe was eight inches below grade, connected to the low pressure sensor. The pipeline was shutdown, isolated the pump station and began the clean up of the released oil. Made repair by replacing the .75 inch pipe with new. Restarted pipeline two hours later. Project was an inspection of station piping performed by our contractor.
Detailed record list
Report Received Date
2013-05-23 00:00:00
Iyear
2013
Report Number
20130180
Supplemental Number
18097
Report Type
Original Final
Operator Id
Name
Shell Pipeline Co., L.p.
Operator Street Address
150 North Dairy Ashford Road Wck Bldg. A
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77079
Local Datetime
2013-05-06 07:30:00
Location Latitude
Location Longitude
-120.3564278
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.69
Recovered Bbls
0.69
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Incident Identified Datetime
2013-05-06 07:30:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-05-06 07:32:00
Restart Datetime
2013-05-06 09:37:00
On Site Datetime
2013-05-06 07:30:00
Nrc Rpt Datetime
2013-05-06 07:32:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Coalinga Pump Station
Segment Name
North 20 - Coalinga To Avon
Onshore State Abbreviation
Ca
Onshore Postal Code
93210
Onshore City Name
Coalinga
Onshore County Name
Fresno
Designated Location
Milepost/valve Station
Designated Name
55.8
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Pipe Facility Type
Intrastate
Item Involved
Auxiliary Piping (E.g. Drain Lines)
Release Type
Leak
Leak Type
Crack
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
0
Est Cost Prop Damage
500
Est Cost Emergency
500
Est Cost Environmental
0
Est Cost Other
0
Prpty
1000
Pipeline Function
> 20% Smys Regulated Transmission
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Operator's Contractor (Second Party)
Ex Party Type
Excavation Damage By Operator's Contractor (Second Party)
Notify Cga Dirt
No
Pipeline Easement Row Ind
Yes
Excavator Type
Contractor
Excavator Equipment
Backhoe/trackhoe
Work Performed
Liquid Pipeline
One Call Notified Ind
Yes
One Call Ticket Num
174556
One Call Center Name
Usa North
Locator Type
Contract Locator
Visible Marks
Yes
Service Interruption
Yes
Service Interruption Hours
2
Root Cause Category
Excavation Issue
Root Cause Type
Improper Excavation Practice Not Listed Above
Preparer Name
R****** K*****
Preparer Title
Regulatory Specialist
Preparer Email
R*************@s****.com
Preparer Telephone
713 241 1064
Prepared Date
2013-05-23 00:00:00
Authorizer Name
B**** S*******
Authorizer Telephone
713 241 3620
Authorizer Title
Manager Integrity And Regulatory Services
Authorizer Email
B*************@s****.com
Narrative
Excavation was being performed around the suction line of the mainline pump station. There was asphalt in an area that needed to excavated. Used the backhoe to lift the asphalt. The backhoe bucket contacted the small diameter .75 inch pipe nipple and cracked the threads. The backhoe operator felt the contact and stopped. The pipe was eight inches below grade, connected to the low pressure sensor. The pipeline was shutdown, isolated the pump station and began the clean up of the released oil. Made repair by replacing the .75 inch pipe with new. Restarted pipeline two hours later. Project was an inspection of station piping performed by our contractor.
Report Received Date 2013-05-23 00:00:00
Iyear 2013
Report Number 20130180
Supplemental Number 18097
Report Type Original Final
Operator Id 31174 PHMSA Enforcement
Name Shell Pipeline Co., L.p.
Operator Street Address 150 North Dairy Ashford Road Wck Bldg. A
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77079
Local Datetime 2013-05-06 07:30:00
Location Latitude 36.18977222 Google Maps OpenStreetMap
Location Longitude -120.3564278 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 0.69
Recovered Bbls 0.69
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Incident Identified Datetime 2013-05-06 07:30:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2013-05-06 07:32:00
Restart Datetime 2013-05-06 09:37:00
On Site Datetime 2013-05-06 07:30:00
Nrc Rpt Datetime 2013-05-06 07:32:00
Nrc Rpt Num 1046179 NRC Report How to search
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name Coalinga Pump Station
Segment Name North 20 - Coalinga To Avon
Onshore State Abbreviation Ca
Onshore Postal Code 93210
Onshore City Name Coalinga
Onshore County Name Fresno
Designated Location Milepost/valve Station
Designated Name 55.8
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Pipe Facility Type Intrastate
Item Involved Auxiliary Piping (E.g. Drain Lines)
Release Type Leak
Leak Type Crack
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 0
Est Cost Prop Damage 500
Est Cost Emergency 500
Est Cost Environmental 0
Est Cost Other 0
Prpty 1000
Pipeline Function > 20% Smys Regulated Transmission
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Operator's Contractor (Second Party)
Ex Party Type Excavation Damage By Operator's Contractor (Second Party)
Notify Cga Dirt No
Pipeline Easement Row Ind Yes
Excavator Type Contractor
Excavator Equipment Backhoe/trackhoe
Work Performed Liquid Pipeline
One Call Notified Ind Yes
One Call Ticket Num 174556
One Call Center Name Usa North
Locator Type Contract Locator
Visible Marks Yes
Service Interruption Yes
Service Interruption Hours 2
Root Cause Category Excavation Issue
Root Cause Type Improper Excavation Practice Not Listed Above
Preparer Name R****** K*****
Preparer Title Regulatory Specialist
Preparer Email R*************@s****.com
Preparer Telephone 713 241 1064
Prepared Date 2013-05-23 00:00:00
Authorizer Name B**** S*******
Authorizer Telephone 713 241 3620
Authorizer Title Manager Integrity And Regulatory Services
Authorizer Email B*************@s****.com
Narrative Excavation was being performed around the suction line of the mainline pump station. There was asphalt in an area that needed to excavated. Used the backhoe to lift the asphalt. The backhoe bucket contacted the small diameter .75 inch pipe nipple and cracked the threads. The backhoe operator felt the contact and stopped. The pipe was eight inches below grade, connected to the low pressure sensor. The pipeline was shutdown, isolated the pump station and began the clean up of the released oil. Made repair by replacing the .75 inch pipe with new. Restarted pipeline two hours later. Project was an inspection of station piping performed by our contractor.