GD incident on 2010-11-12 — NY
Operator
Consolidated Edison Co Of New York
Cause
Other Outside Force Damage
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$1,200
Incident datetime
2010-11-12 09:52
Report number
Location
NY
Narrative
On november 12, 2010, at 09:52 the new york city fire deptartment (fdny) reported a contractor damage at 490 hunts point ave., bronx, new york to the gas emergency response center (gerc). The fdny stated that they were evacuating surrounding properties. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), gas emergency response group (erg), construction emergency response force (erf) and bronx gas operations supervision. A third party fork lift (operated by luis mejia, an employee of hernandez products corporation) hit a transmission pressure gauge post causing a leak at transmission pressure on a 1" steel gauge line. Gds shut main valve 7735 (4" transmission inlet valve to regulator station gr-184) at 10:04 hrs. To secure the leak. The fdny evacuated 10 people from the signature savings bank at 423 hunts point ave. And 6 people from hernandez products corporation at 490 hunts point ave. Prior to gds' arrival, and the evacuation ended at 10:18. Gds, construction and pressure control responded to location. Construction cut and capped the line, welders secured the piping, repairs were made and x-rayed, and the station and effected pipeline were placed back in service at 17:03 hours. This incident had no impact on the transmission or distribution systems. There were no reported injuries, no outages, and no media attention.The US DOT, nys psc and nyc dep were notified. This was an upgraded level incident. Note--this gas distribution incident report was created in place of rescinded gas transmission incident report #20100094-15866.
Detailed record list
Occurred At
2010-11-12 09:52:00
Year
2010
Report Received Date
2013-05-22 00:00:00
Iyear
2010.0
Report Number
20130052.0
Supplemental Number
15658.0
Report Type
Original
Operator Id
2704
Name
Consolidated Edison Co Of New York
Operator Street Address
4 Irving Place
Operator City Name
New York
Operator State Abbreviation
NY
Operator Postal Code
10003
Local Datetime
2010-11-12 09:52:00
Location Street Address
490 Hunts Point Avenue
Location City Name
Bronx
Location State Abbreviation
NY
Location Postal Code
10474-7012
Location Latitude
40.810353
Location Longitude
-73.88104
Nrc Rpt Datetime
2010-11-12 10:25:00
Commodity Released Type
Natural Gas
Unintentional Release
17.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
16.0
Incident Identified Datetime
2010-11-12 09:52:00
On Site Datetime
2010-11-12 10:04:00
Federal
No
Location Type
Utility Right-Of-Way / Easement
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance (E.g. Value Or Regulator Station, Outdoor Meter Set)
Crossing
No
Pipe Facility Type
Privately Owned
System Part Involved
District Regulator/metering Station
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Unknown
Release Type
Other
Release Type Details
Damage By Vehicle/equipment
Class Location Type
Class 4 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
1200.0
Est Cost Emergency
4174.0
Est Cost Other
0.0
Est Cost Other Details
0
Est Cost Unintentional Release
100.0
Prpty
5474.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
0.0
Accident Psig
280.0
Normal Psig
280.0
Mop Psig
350.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
No
Accident Identifier
Notification From Emergency Responder
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype
Third Party
Preparer Name
K**** F****
Preparer Title
Manager-Gas Emergency Response Center
Preparer Email
F*****@c****.com
Preparer Telephone
718-319-2310
Preparer Fax
718-904-4607
Authorizer Name
V***** D******
Authorizer Title
Dept. Manager-Gas Emergency Response Center
Authorizer Telephone
718-319-2310
Authorizer Email
D*******@c****.com
Narrative
On november 12, 2010, at 09:52 the new york city fire deptartment (fdny) reported a contractor damage at 490 hunts point ave., bronx, new york to the gas emergency response center (gerc). The fdny stated that they were evacuating surrounding properties. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), gas emergency response group (erg), construction emergency response force (erf) and bronx gas operations supervision. A third party fork lift (operated by luis mejia, an employee of hernandez products corporation) hit a transmission pressure gauge post causing a leak at transmission pressure on a 1" steel gauge line. Gds shut main valve 7735 (4" transmission inlet valve to regulator station gr-184) at 10:04 hrs. To secure the leak. The fdny evacuated 10 people from the signature savings bank at 423 hunts point ave. And 6 people from hernandez products corporation at 490 hunts point ave. Prior to gds' arrival, and the evacuation ended at 10:18. Gds, construction and pressure control responded to location. Construction cut and capped the line, welders secured the piping, repairs were made and x-rayed, and the station and effected pipeline were placed back in service at 17:03 hours. This incident had no impact on the transmission or distribution systems. There were no reported injuries, no outages, and no media attention.The US DOT, nys psc and nyc dep were notified. This was an upgraded level incident. Note--this gas distribution incident report was created in place of rescinded gas transmission incident report #20100094-15866.
| Occurred At | 2010-11-12 09:52:00 |
|---|---|
| Year | 2010 |
| Report Received Date | 2013-05-22 00:00:00 |
| Iyear | 2010.0 |
| Report Number | 20130052.0 |
| Supplemental Number | 15658.0 |
| Report Type | Original |
| Operator Id | 2704 PHMSA Enforcement |
| Name | Consolidated Edison Co Of New York |
| Operator Street Address | 4 Irving Place |
| Operator City Name | New York |
| Operator State Abbreviation | NY |
| Operator Postal Code | 10003 |
| Local Datetime | 2010-11-12 09:52:00 |
| Location Street Address | 490 Hunts Point Avenue |
| Location City Name | Bronx |
| Location State Abbreviation | NY |
| Location Postal Code | 10474-7012 |
| Location Latitude | 40.810353 Google Maps OpenStreetMap |
| Location Longitude | -73.88104 Google Maps OpenStreetMap |
| Nrc Rpt Datetime | 2010-11-12 10:25:00 |
| Commodity Released Type | Natural Gas |
| Unintentional Release | 17.0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 16.0 |
| Incident Identified Datetime | 2010-11-12 09:52:00 |
| On Site Datetime | 2010-11-12 10:04:00 |
| Federal | No |
| Location Type | Utility Right-Of-Way / Easement |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance (E.g. Value Or Regulator Station, Outdoor Meter Set) |
| Crossing | No |
| Pipe Facility Type | Privately Owned |
| System Part Involved | District Regulator/metering Station |
| Material Involved | Steel |
| Steel Seam Type | Other |
| Steel Seam Type Details | Unknown |
| Release Type | Other |
| Release Type Details | Damage By Vehicle/equipment |
| Class Location Type | Class 4 Location |
| Est Cost Oper Paid | 0.0 |
| Est Cost Prop Damage | 1200.0 |
| Est Cost Emergency | 4174.0 |
| Est Cost Other | 0.0 |
| Est Cost Other Details | 0 |
| Est Cost Unintentional Release | 100.0 |
| Prpty | 5474.0 |
| Commercial Affected | 0.0 |
| Industrial Affected | 0.0 |
| Residences Affected | 0.0 |
| Accident Psig | 280.0 |
| Normal Psig | 280.0 |
| Mop Psig | 350.0 |
| Accident Pressure | Pressure Did Not Exceed Maop |
| Scada In Place Ind | No |
| Accident Identifier | Notification From Emergency Responder |
| Investigation Status | No, the facility was not monitored by a controller(s) at the time of the incident |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Other Outside Force Damage |
| Cause Details | Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation |
| Outside Force Type | Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation |
| Vehicle Subtype | Third Party |
| Preparer Name | K**** F**** |
| Preparer Title | Manager-Gas Emergency Response Center |
| Preparer Email | F*****@c****.com |
| Preparer Telephone | 718-319-2310 |
| Preparer Fax | 718-904-4607 |
| Authorizer Name | V***** D****** |
| Authorizer Title | Dept. Manager-Gas Emergency Response Center |
| Authorizer Telephone | 718-319-2310 |
| Authorizer Email | D*******@c****.com |
| Narrative | On november 12, 2010, at 09:52 the new york city fire deptartment (fdny) reported a contractor damage at 490 hunts point ave., bronx, new york to the gas emergency response center (gerc). The fdny stated that they were evacuating surrounding properties. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), gas emergency response group (erg), construction emergency response force (erf) and bronx gas operations supervision. A third party fork lift (operated by luis mejia, an employee of hernandez products corporation) hit a transmission pressure gauge post causing a leak at transmission pressure on a 1" steel gauge line. Gds shut main valve 7735 (4" transmission inlet valve to regulator station gr-184) at 10:04 hrs. To secure the leak. The fdny evacuated 10 people from the signature savings bank at 423 hunts point ave. And 6 people from hernandez products corporation at 490 hunts point ave. Prior to gds' arrival, and the evacuation ended at 10:18. Gds, construction and pressure control responded to location. Construction cut and capped the line, welders secured the piping, repairs were made and x-rayed, and the station and effected pipeline were placed back in service at 17:03 hours. This incident had no impact on the transmission or distribution systems. There were no reported injuries, no outages, and no media attention.The US DOT, nys psc and nyc dep were notified. This was an upgraded level incident. Note--this gas distribution incident report was created in place of rescinded gas transmission incident report #20100094-15866. |