GD incident on 2013-01-15 — IL

Operator
Liberty Energy (Mid-States) Corp D/b/a Liberty Utilities - Central
Cause
Equipment Failure
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$85,000
Incident datetime
2013-01-15 06:45
Report number
Location
IL, MASSAC
Narrative
A fisher 630 regulator failed and the fisher 1805p-167ar relief valve failed to relieve. This resulted in 270 psig being placed on the existing plastic pe distribution system (system). The system was shut down. A 15psi air test was placed on the system then the system was re-pressurized with natural gas to 15 psig, leak surveyed and then temporarily placed back into service until the entire system was replaced. During the replacement the existing system was leak surveyed each day until all customers were back in service. The house piping was air tested to ensure all their piping was safe along with visual inspecting all accessible piping. Total pipe replacement - 8,102 ft of 2" poly and 28 poly services (5,193').
Detailed record list
Occurred At
2013-01-15 06:45:00
Year
2013
Report Received Date
2013-02-11 00:00:00
Iyear
2013.0
Report Number
20130014.0
Supplemental Number
15602.0
Report Type
Original Final
Operator Id
Name
Liberty Energy (Mid-States) Corp D/b/a Liberty Utilities - Central
Operator Street Address
2751 North High Street
Operator City Name
Jackson
Operator State Abbreviation
MO
Operator Postal Code
63755
Local Datetime
2013-01-15 06:20:00
Location Street Address
Mt. Mission Rd.
Location City Name
Metropolis
Location County Name
Massac
Location State Abbreviation
IL
Location Postal Code
62960
Location Latitude
Location Longitude
Nrc Rpt Datetime
2013-01-15 10:30:00
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
1.3
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0.0
Incident Identified Datetime
2013-01-15 06:45:00
On Site Datetime
2013-01-15 07:10:00
Federal
No
Location Type
Utility Right-Of-Way / Easement
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance (E.g. Value Or Regulator Station, Outdoor Meter Set)
Crossing
No
Pipe Facility Type
Privately Owned
System Part Involved
District Regulator/metering Station
Installation Year
1980.0
Material Involved
Cast/wrought Iron
Release Type
Other
Release Type Details
Fisher 630 Regulator Failed At The Same Time 1805p-167ar Pilot Failed To Relieve.
Class Location Type
Class 3 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
85000.0
Est Cost Emergency
1000.0
Est Cost Other
0.0
Est Cost Unintentional Release
3.0
Prpty
86003.0
Commercial Affected
0.0
Industrial Affected
1.0
Residences Affected
27.0
Accident Psig
270.0
Normal Psig
70.0
Mop Psig
80.0
Accident Pressure
Pressure Exceeded The Applicable Allowance In 192.201
Scada In Place Ind
No
Accident Identifier
Notification From Public
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Malfunction Of Control/relief Equipment
Eq Failure Type
Malfunction Of Control/relief Equipment
Relief Valve Ind
Yes
Pressure Regulator Ind
Yes
Preparer Name
R***** S*****
Preparer Title
Compliance Manager
Preparer Email
R************@l***************.com
Preparer Telephone
573-225-7834
Preparer Fax
573-471-1363
Authorizer Name
M****** D* B*****
Authorizer Title
Sr. Manager - Engineering And Compliance
Authorizer Telephone
573-979-0220
Authorizer Email
M**********@l***************.com
Narrative
A fisher 630 regulator failed and the fisher 1805p-167ar relief valve failed to relieve. This resulted in 270 psig being placed on the existing plastic pe distribution system (system). The system was shut down. A 15psi air test was placed on the system then the system was re-pressurized with natural gas to 15 psig, leak surveyed and then temporarily placed back into service until the entire system was replaced. During the replacement the existing system was leak surveyed each day until all customers were back in service. The house piping was air tested to ensure all their piping was safe along with visual inspecting all accessible piping. Total pipe replacement - 8,102 ft of 2" poly and 28 poly services (5,193').
Occurred At 2013-01-15 06:45:00
Year 2013
Report Received Date 2013-02-11 00:00:00
Iyear 2013.0
Report Number 20130014.0
Supplemental Number 15602.0
Report Type Original Final
Operator Id 38906 PHMSA Enforcement
Name Liberty Energy (Mid-States) Corp D/b/a Liberty Utilities - Central
Operator Street Address 2751 North High Street
Operator City Name Jackson
Operator State Abbreviation MO
Operator Postal Code 63755
Local Datetime 2013-01-15 06:20:00
Location Street Address Mt. Mission Rd.
Location City Name Metropolis
Location County Name Massac
Location State Abbreviation IL
Location Postal Code 62960
Location Latitude 37.191143 Google Maps OpenStreetMap
Location Longitude -88.759725 Google Maps OpenStreetMap
Nrc Rpt Datetime 2013-01-15 10:30:00
Nrc Rpt Num 1035738 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 1.3
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0.0
Incident Identified Datetime 2013-01-15 06:45:00
On Site Datetime 2013-01-15 07:10:00
Federal No
Location Type Utility Right-Of-Way / Easement
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance (E.g. Value Or Regulator Station, Outdoor Meter Set)
Crossing No
Pipe Facility Type Privately Owned
System Part Involved District Regulator/metering Station
Installation Year 1980.0
Material Involved Cast/wrought Iron
Release Type Other
Release Type Details Fisher 630 Regulator Failed At The Same Time 1805p-167ar Pilot Failed To Relieve.
Class Location Type Class 3 Location
Est Cost Oper Paid 0.0
Est Cost Prop Damage 85000.0
Est Cost Emergency 1000.0
Est Cost Other 0.0
Est Cost Unintentional Release 3.0
Prpty 86003.0
Commercial Affected 0.0
Industrial Affected 1.0
Residences Affected 27.0
Accident Psig 270.0
Normal Psig 70.0
Mop Psig 80.0
Accident Pressure Pressure Exceeded The Applicable Allowance In 192.201
Scada In Place Ind No
Accident Identifier Notification From Public
Investigation Status No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Malfunction Of Control/relief Equipment
Eq Failure Type Malfunction Of Control/relief Equipment
Relief Valve Ind Yes
Pressure Regulator Ind Yes
Preparer Name R***** S*****
Preparer Title Compliance Manager
Preparer Email R************@l***************.com
Preparer Telephone 573-225-7834
Preparer Fax 573-471-1363
Authorizer Name M****** D* B*****
Authorizer Title Sr. Manager - Engineering And Compliance
Authorizer Telephone 573-979-0220
Authorizer Email M**********@l***************.com
Narrative A fisher 630 regulator failed and the fisher 1805p-167ar relief valve failed to relieve. This resulted in 270 psig being placed on the existing plastic pe distribution system (system). The system was shut down. A 15psi air test was placed on the system then the system was re-pressurized with natural gas to 15 psig, leak surveyed and then temporarily placed back into service until the entire system was replaced. During the replacement the existing system was leak surveyed each day until all customers were back in service. The house piping was air tested to ensure all their piping was safe along with visual inspecting all accessible piping. Total pipe replacement - 8,102 ft of 2" poly and 28 poly services (5,193').