HL incident on 2012-11-20 — TX

Operator
Enbridge Energy, Limited Partnership
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$2,000,000
Incident datetime
2012-11-20 14:33
Report number
Location
TX
Narrative
Enbridge's edmonton control center received a call on november 20, 2012 at approximately 12:48 local time, from bp chicap personnel at the mokena delivery site, indicating they were investigating oil on the ground within the facility. Bp made the initial call to the nrc as documented in part a #4 on the PHMSA f 7000-1. Enbridge's line 6a and line 14 each have a delivery line into this facility. At the time of bp's call into enbridge's ecc, line 6a was not delivering into mokena, and line 14 was delivering to the exxon mobil facility at mokena. Line 14 was shut down until further investigation of the release source could be completed by bp chicap and enbridge field personnel. Enbridge personnel discovered the leak was in the area of tank 12, near the location of an enbridge relief line. All delivery and relief lines from the adjacent enbridge station to bp chicap were locked out until field personnel could positively identify the source of the oil. On november 21 at approximately 18:00 the leak was confirmed to be on the enbridge relief line near tank 12. The relief line piping was manufactured by uss and is comprised of 20" diameter pipe by 0.250" nominal wall thickness, API 5l grade x42 line pipe steel that was installed in 1993 with a high frequency electric resistance welded seam and fusion bond epoxy coating. When it was discovered that the leak was on the enbridge relief line, enbridge completed a call to the nrc at 19:14 on november 21, nrc# 1031299 as documented in part a #7. Further investigation of the source of oil revealed that there was no check valve and the relief line was exposed to head pressure from tank 13. In order to provide alternate safe delivery operations to exxon mobil at the mokena facility while the pressure relief system is out of service for repair, a temporary procedure was developed until the relief lines are back in operation. The initial piece of failed piping was cut out and has been replaced. It was suspected at the time the cause of the failure was internal corrosion, due to the failure occurring in a low spot. At the same time this repair was done, enbridge started an elevation study to identify other low spots on the relief line and to determine if internal corrosion may exist in other locations. A defect was discovered during sandblasting in preparation for nde. That segment was cut out and replaced. Nde confirmed pipe integrity at all other tested locations with the exception of the line near tank 13, which was not completely excavated. A flange and blind was installed to isolate the relief line upstream of the aforementioned piping to tank 13. A hydrotest was successfully completed on the segment of the relief line to tank 11, and that segment has been placed back into service. Repairs continue and it is anticipated they will be complete by the end of first quarter 2013. Cleanup and restoration of the site is in progress and it is anticipated to be completed by the end of january 2013. Update - 5/7/13 metallurgical analysis confirmed internal corrosion as the cause. Repairs, clean up and restoration have been completed with the exception of a separate section of this line that ties into a different tank as a back-up in case bp takes their tank out of service. An outage is scheduled for july 24, 2013 to complete this work. Approximately 20,200 yards of contaminated soil has been removed from the release site. Update - 9/27/13 scheduled outage was pushed back with a new completion date of october 9, 2013. Update - 4/22/14 the final repair work was successfully completed on march 24, 2014.
Detailed record list
Report Received Date
2012-12-20 00:00:00
Iyear
2012
Report Number
20120369
Supplemental Number
20541
Report Type
Supplemental Final
Operator Id
Name
Enbridge Energy, Limited Partnership
Operator Street Address
915 N Eldridge Parkway, Suite 1100
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77079
Local Datetime
2012-11-20 14:33:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
900
Recovered Bbls
900
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2012-11-20 14:33:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2012-11-20 14:48:00
Restart Datetime
2012-11-20 21:30:00
On Site Datetime
2012-11-20 14:33:00
Nrc Rpt Datetime
2012-11-21 19:14:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Enbridge Line 6a And 14 Pressure Relieve Line
Segment Name
Pressure Relief Line To Mokena
Onshore State Abbreviation
Il
Onshore Postal Code
60448
Onshore City Name
Mokena
Onshore County Name
Will
Designated Location
Milepost/valve Station
Designated Name
Mk
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
72
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Relief Line And Relief Equipment
Installation Year
1993
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
0
Est Cost Prop Damage
2000000
Est Cost Emergency
300000
Est Cost Environmental
5500000
Est Cost Other
2000000
Est Cost Other Details
Integrity Analysis And Inspections/hydrotesting
Prpty
9800000
Accident Psig
40
Mop Psig
275
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Localized Pitting
Int Water Acid Ind
Yes
Int Microbiological Ind
Yes
Int Field Exam Basis Ind
Yes
Int Metallurgical Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
No
Corrosion Lining
No
Cleaning Dewatering
Not Applicable - Not Mainline Pipe
Corrosion Coupons
Not Applicable - Not Mainline Pipe
Preparer Name
S**** S****
Preparer Title
Compliance Analyst
Preparer Email
S**********@e*******.com
Preparer Telephone
218-464-5754
Preparer Fax
218-464-5992
Prepared Date
2015-06-24 00:00:00
Authorizer Name
R** C*******
Authorizer Telephone
218-464-5743
Authorizer Title
Manager Us Pipeline Compliance
Authorizer Email
R***********@e*******.com
Narrative
Enbridge's edmonton control center received a call on november 20, 2012 at approximately 12:48 local time, from bp chicap personnel at the mokena delivery site, indicating they were investigating oil on the ground within the facility. Bp made the initial call to the nrc as documented in part a #4 on the PHMSA f 7000-1. Enbridge's line 6a and line 14 each have a delivery line into this facility. At the time of bp's call into enbridge's ecc, line 6a was not delivering into mokena, and line 14 was delivering to the exxon mobil facility at mokena. Line 14 was shut down until further investigation of the release source could be completed by bp chicap and enbridge field personnel. Enbridge personnel discovered the leak was in the area of tank 12, near the location of an enbridge relief line. All delivery and relief lines from the adjacent enbridge station to bp chicap were locked out until field personnel could positively identify the source of the oil. On november 21 at approximately 18:00 the leak was confirmed to be on the enbridge relief line near tank 12. The relief line piping was manufactured by uss and is comprised of 20" diameter pipe by 0.250" nominal wall thickness, API 5l grade x42 line pipe steel that was installed in 1993 with a high frequency electric resistance welded seam and fusion bond epoxy coating. When it was discovered that the leak was on the enbridge relief line, enbridge completed a call to the nrc at 19:14 on november 21, nrc# 1031299 as documented in part a #7. Further investigation of the source of oil revealed that there was no check valve and the relief line was exposed to head pressure from tank 13. In order to provide alternate safe delivery operations to exxon mobil at the mokena facility while the pressure relief system is out of service for repair, a temporary procedure was developed until the relief lines are back in operation. The initial piece of failed piping was cut out and has been replaced. It was suspected at the time the cause of the failure was internal corrosion, due to the failure occurring in a low spot. At the same time this repair was done, enbridge started an elevation study to identify other low spots on the relief line and to determine if internal corrosion may exist in other locations. A defect was discovered during sandblasting in preparation for nde. That segment was cut out and replaced. Nde confirmed pipe integrity at all other tested locations with the exception of the line near tank 13, which was not completely excavated. A flange and blind was installed to isolate the relief line upstream of the aforementioned piping to tank 13. A hydrotest was successfully completed on the segment of the relief line to tank 11, and that segment has been placed back into service. Repairs continue and it is anticipated they will be complete by the end of first quarter 2013. Cleanup and restoration of the site is in progress and it is anticipated to be completed by the end of january 2013. Update - 5/7/13 metallurgical analysis confirmed internal corrosion as the cause. Repairs, clean up and restoration have been completed with the exception of a separate section of this line that ties into a different tank as a back-up in case bp takes their tank out of service. An outage is scheduled for july 24, 2013 to complete this work. Approximately 20,200 yards of contaminated soil has been removed from the release site. Update - 9/27/13 scheduled outage was pushed back with a new completion date of october 9, 2013. Update - 4/22/14 the final repair work was successfully completed on march 24, 2014.
Report Received Date 2012-12-20 00:00:00
Iyear 2012
Report Number 20120369
Supplemental Number 20541
Report Type Supplemental Final
Operator Id 11169 PHMSA Enforcement
Name Enbridge Energy, Limited Partnership
Operator Street Address 915 N Eldridge Parkway, Suite 1100
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77079
Local Datetime 2012-11-20 14:33:00
Location Latitude 41.55556 Google Maps OpenStreetMap
Location Longitude -87.88528 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 900
Recovered Bbls 900
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2012-11-20 14:33:00
System Part Involved Onshore Terminal/tank Farm Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2012-11-20 14:48:00
Restart Datetime 2012-11-20 21:30:00
On Site Datetime 2012-11-20 14:33:00
Nrc Rpt Datetime 2012-11-21 19:14:00
Nrc Rpt Num 1031299 NRC Report How to search
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name Enbridge Line 6a And 14 Pressure Relieve Line
Segment Name Pressure Relief Line To Mokena
Onshore State Abbreviation Il
Onshore Postal Code 60448
Onshore City Name Mokena
Onshore County Name Will
Designated Location Milepost/valve Station
Designated Name Mk
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 72
Crossing No
Pipe Facility Type Interstate
Item Involved Relief Line And Relief Equipment
Installation Year 1993
Material Involved Carbon Steel
Release Type Leak
Leak Type Pinhole
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 0
Est Cost Prop Damage 2000000
Est Cost Emergency 300000
Est Cost Environmental 5500000
Est Cost Other 2000000
Est Cost Other Details Integrity Analysis And Inspections/hydrotesting
Prpty 9800000
Accident Psig 40
Mop Psig 275
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details Internal Corrosion
Internal External Internal Corrosion
Int Visual Exam Results Localized Pitting
Int Water Acid Ind Yes
Int Microbiological Ind Yes
Int Field Exam Basis Ind Yes
Int Metallurgical Basis Ind Yes
Int Low Point Pipe Loc Ind Yes
Corrosion Inhibitors No
Corrosion Lining No
Cleaning Dewatering Not Applicable - Not Mainline Pipe
Corrosion Coupons Not Applicable - Not Mainline Pipe
Preparer Name S**** S****
Preparer Title Compliance Analyst
Preparer Email S**********@e*******.com
Preparer Telephone 218-464-5754
Preparer Fax 218-464-5992
Prepared Date 2015-06-24 00:00:00
Authorizer Name R** C*******
Authorizer Telephone 218-464-5743
Authorizer Title Manager Us Pipeline Compliance
Authorizer Email R***********@e*******.com
Narrative Enbridge's edmonton control center received a call on november 20, 2012 at approximately 12:48 local time, from bp chicap personnel at the mokena delivery site, indicating they were investigating oil on the ground within the facility. Bp made the initial call to the nrc as documented in part a #4 on the PHMSA f 7000-1. Enbridge's line 6a and line 14 each have a delivery line into this facility. At the time of bp's call into enbridge's ecc, line 6a was not delivering into mokena, and line 14 was delivering to the exxon mobil facility at mokena. Line 14 was shut down until further investigation of the release source could be completed by bp chicap and enbridge field personnel. Enbridge personnel discovered the leak was in the area of tank 12, near the location of an enbridge relief line. All delivery and relief lines from the adjacent enbridge station to bp chicap were locked out until field personnel could positively identify the source of the oil. On november 21 at approximately 18:00 the leak was confirmed to be on the enbridge relief line near tank 12. The relief line piping was manufactured by uss and is comprised of 20" diameter pipe by 0.250" nominal wall thickness, API 5l grade x42 line pipe steel that was installed in 1993 with a high frequency electric resistance welded seam and fusion bond epoxy coating. When it was discovered that the leak was on the enbridge relief line, enbridge completed a call to the nrc at 19:14 on november 21, nrc# 1031299 as documented in part a #7. Further investigation of the source of oil revealed that there was no check valve and the relief line was exposed to head pressure from tank 13. In order to provide alternate safe delivery operations to exxon mobil at the mokena facility while the pressure relief system is out of service for repair, a temporary procedure was developed until the relief lines are back in operation. The initial piece of failed piping was cut out and has been replaced. It was suspected at the time the cause of the failure was internal corrosion, due to the failure occurring in a low spot. At the same time this repair was done, enbridge started an elevation study to identify other low spots on the relief line and to determine if internal corrosion may exist in other locations. A defect was discovered during sandblasting in preparation for nde. That segment was cut out and replaced. Nde confirmed pipe integrity at all other tested locations with the exception of the line near tank 13, which was not completely excavated. A flange and blind was installed to isolate the relief line upstream of the aforementioned piping to tank 13. A hydrotest was successfully completed on the segment of the relief line to tank 11, and that segment has been placed back into service. Repairs continue and it is anticipated they will be complete by the end of first quarter 2013. Cleanup and restoration of the site is in progress and it is anticipated to be completed by the end of january 2013. Update - 5/7/13 metallurgical analysis confirmed internal corrosion as the cause. Repairs, clean up and restoration have been completed with the exception of a separate section of this line that ties into a different tank as a back-up in case bp takes their tank out of service. An outage is scheduled for july 24, 2013 to complete this work. Approximately 20,200 yards of contaminated soil has been removed from the release site. Update - 9/27/13 scheduled outage was pushed back with a new completion date of october 9, 2013. Update - 4/22/14 the final repair work was successfully completed on march 24, 2014.

All rights reserved. Copyright © by ClearPHMSA