HL incident on 2012-11-06 — OK

Operator
Oneok Ngl Pipeline, Llc
Cause
Material Failure Of Pipe Or Weld
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$332,463
Incident datetime
2012-11-06 12:00
Report number
Location
OK
Narrative
As a result of an inline inspection (ili) on feb 12, 2012, this seam weld anomaly was selected for a direct examination and evaluation. The feature at this site was predicted to be 16% wall loss. Because the anomaly was located inside a casing, a project was put in place to cut out the anomaly and replace the section with new pipe, and with evaluation of the anomaly to be performed after the replacement was completed. On october 31, 2012, the area operations employee visited the proposed dig site at wolf road pipeline crossing to evaluate the scope of work for the upcoming anomaly investigation. While on site, the employee identified staining on the vent pipe and did a lel test, which tested positive for hydrocarbons. Initial samples were gathered by siphoning a sample from the vent pipe and analyzed by a third party. The analysis identified characteristics consistent with naptha, which was not a product being transported by that pipeline. With this information, oneok proceeded with the preparation for the anomaly excavation. On nov. 1, the pipeline was shutdown at approximately 1:00 a.M. And purged with nitrogen to allow the removal of the pipe in that casing and evaluate the anomaly. Although oneok did not believe at the time that there had been a release from its pipeline, the contaminated soil from the excavation was loaded into roll-off containers and sent to a disposal site. On nov. 3-4, the pipeline section containing the anomaly was removed from casing and new pipe installed through the existing casing. The pipeline was returned to service at 12:00 p.M. On nov. 4. A third party contractor was retained to remove the asbestos coating from the cut-out section, which was completed on nov. 5. On nov. 6, oneok's contract inspector arrived and completed nde of the anomaly. The contractor determined the defect was through-wall and not 16% wall loss, as had been indicated in the ili report. Based on this new information, the lab analysis was re-evaluated on nov. 7, and it was determined that the characteristics were similar enough to the oneok product in the pipeline to consider it a match. On nov. 8, the oneok environmental group notified the oneok compliance group that costs to remove and dispose of the contaminated soil would exceed $50,000. Based on this information, along with the evaluation identifying the through-wall crack in the removed section, oneok immediately made a report to nrc. The pipe samples were submitted to kiefner & associates for metallurgical analysis. The analysis determined a mill-related lack of fusion in the seam weld as root cause.
Detailed record list
Report Received Date
2012-11-29 00:00:00
Iyear
2012
Report Number
20120337
Supplemental Number
21762
Report Type
Supplemental Final
Operator Id
Name
Oneok Ngl Pipeline, Llc
Operator Street Address
100 West Fifth Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2012-10-31 10:00:00
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Other
Commodity Details
14# Natural Gasoline
Unintentional Release Bbls
10
Intentional Release Bbls
0
Recovered Bbls
10
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2012-11-06 12:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2012-11-01 01:06:00
Restart Datetime
2012-11-04 12:00:00
On Site Datetime
2012-10-31 10:00:00
Nrc Rpt Datetime
2012-11-08 18:58:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
106e Pipeline
Segment Name
Oneok Index # 11106
Onshore State Abbreviation
Il
Onshore Postal Code
60467
Onshore City Name
Orland Park
Onshore County Name
Cook
Designated Location
Survey Station No.
Designated Name
1940+38
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
144
Crossing
Yes
Road Crossing Ind
Yes
Road Type
Cased
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Seam
Pipe Diameter
8
Pipe Wall Thickness
0.25
Pipe Smys
52000
Pipe Specification
Api 5l
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Ipsco
Pipe Coating Type
Coal Tar
Installation Year
1967
Manufactured Year
1963
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Crack
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
1000
Est Cost Prop Damage
332463
Est Cost Emergency
0
Est Cost Environmental
90000
Est Cost Other
0
Prpty
423463
Accident Psig
946
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
18058
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind
Yes
Invest No Schedule Ind Details
Controller Actions Did Not Cause Or Contribute To Event
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Material Failure Of Pipe Or Weld
Cause Details
Original Manufacturing-Related (Not Girth Weld Or Other Welds Formed In The Field)
Field Exam Ind
Yes
Metallurgical Ind
Yes
Failure Type
Original Manufacturing-Related (Not Girth Weld Or Other Welds Formed In The Field)
Other Factor
Yes
Other Factor Details
Analyses Determined Lack Of Fusion In Seam
Additional Crack Ind
Yes
Additional Lack Fusion Ind
Yes
Collected Data Ind
Yes
Axial Magnetic Flx Lkg Ind
Yes
Cir Trn Wave Mgn Flx Lkg Ind
Yes
Geometry Deformation Ind
Yes
Axial Recent Year
2008
Circ Wave Recent Year
2011
Geometry Recent Year
2007
Other Recent Year
2011
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
N*** J****
Preparer Title
Regulatory Compliance Coordinator
Preparer Email
N*********@o****.com
Preparer Telephone
580-395-6304
Preparer Fax
580-395-2933
Prepared Date
2016-10-14 00:00:00
Authorizer Name
N*** J****
Authorizer Telephone
580-395-6304
Authorizer Title
Regulatory Compliance Coordinator
Authorizer Email
N*********@o****.com
Narrative
As a result of an inline inspection (ili) on feb 12, 2012, this seam weld anomaly was selected for a direct examination and evaluation. The feature at this site was predicted to be 16% wall loss. Because the anomaly was located inside a casing, a project was put in place to cut out the anomaly and replace the section with new pipe, and with evaluation of the anomaly to be performed after the replacement was completed. On october 31, 2012, the area operations employee visited the proposed dig site at wolf road pipeline crossing to evaluate the scope of work for the upcoming anomaly investigation. While on site, the employee identified staining on the vent pipe and did a lel test, which tested positive for hydrocarbons. Initial samples were gathered by siphoning a sample from the vent pipe and analyzed by a third party. The analysis identified characteristics consistent with naptha, which was not a product being transported by that pipeline. With this information, oneok proceeded with the preparation for the anomaly excavation. On nov. 1, the pipeline was shutdown at approximately 1:00 a.M. And purged with nitrogen to allow the removal of the pipe in that casing and evaluate the anomaly. Although oneok did not believe at the time that there had been a release from its pipeline, the contaminated soil from the excavation was loaded into roll-off containers and sent to a disposal site. On nov. 3-4, the pipeline section containing the anomaly was removed from casing and new pipe installed through the existing casing. The pipeline was returned to service at 12:00 p.M. On nov. 4. A third party contractor was retained to remove the asbestos coating from the cut-out section, which was completed on nov. 5. On nov. 6, oneok's contract inspector arrived and completed nde of the anomaly. The contractor determined the defect was through-wall and not 16% wall loss, as had been indicated in the ili report. Based on this new information, the lab analysis was re-evaluated on nov. 7, and it was determined that the characteristics were similar enough to the oneok product in the pipeline to consider it a match. On nov. 8, the oneok environmental group notified the oneok compliance group that costs to remove and dispose of the contaminated soil would exceed $50,000. Based on this information, along with the evaluation identifying the through-wall crack in the removed section, oneok immediately made a report to nrc. The pipe samples were submitted to kiefner & associates for metallurgical analysis. The analysis determined a mill-related lack of fusion in the seam weld as root cause.
Report Received Date 2012-11-29 00:00:00
Iyear 2012
Report Number 20120337
Supplemental Number 21762
Report Type Supplemental Final
Operator Id 32109 PHMSA Enforcement
Name Oneok Ngl Pipeline, Llc
Operator Street Address 100 West Fifth Street
Operator City Name Tulsa
Operator State Abbreviation OK
Operator Postal Code 74103
Local Datetime 2012-10-31 10:00:00
Location Latitude 41.644119 Google Maps OpenStreetMap
Location Longitude -87.892427 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Other
Commodity Details 14# Natural Gasoline
Unintentional Release Bbls 10
Intentional Release Bbls 0
Recovered Bbls 10
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2012-11-06 12:00:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2012-11-01 01:06:00
Restart Datetime 2012-11-04 12:00:00
On Site Datetime 2012-10-31 10:00:00
Nrc Rpt Datetime 2012-11-08 18:58:00
Nrc Rpt Num 1030091 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name 106e Pipeline
Segment Name Oneok Index # 11106
Onshore State Abbreviation Il
Onshore Postal Code 60467
Onshore City Name Orland Park
Onshore County Name Cook
Designated Location Survey Station No.
Designated Name 1940+38
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Pavement
Depth Of Cover 144
Crossing Yes
Road Crossing Ind Yes
Road Type Cased
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Seam
Pipe Diameter 8
Pipe Wall Thickness 0.25
Pipe Smys 52000
Pipe Specification Api 5l
Pipe Seam Type Erw - High Frequency
Pipe Manufacturer Ipsco
Pipe Coating Type Coal Tar
Installation Year 1967
Manufactured Year 1963
Material Involved Carbon Steel
Release Type Leak
Leak Type Crack
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Usa Drinking Ind Yes
Usa Drinking Yes No Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 1000
Est Cost Prop Damage 332463
Est Cost Emergency 0
Est Cost Environmental 90000
Est Cost Other 0
Prpty 423463
Accident Psig 946
Mop Psig 1440
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 18058
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind Yes
Invest No Schedule Ind Details Controller Actions Did Not Cause Or Contribute To Event
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Material Failure Of Pipe Or Weld
Cause Details Original Manufacturing-Related (Not Girth Weld Or Other Welds Formed In The Field)
Field Exam Ind Yes
Metallurgical Ind Yes
Failure Type Original Manufacturing-Related (Not Girth Weld Or Other Welds Formed In The Field)
Other Factor Yes
Other Factor Details Analyses Determined Lack Of Fusion In Seam
Additional Crack Ind Yes
Additional Lack Fusion Ind Yes
Collected Data Ind Yes
Axial Magnetic Flx Lkg Ind Yes
Cir Trn Wave Mgn Flx Lkg Ind Yes
Geometry Deformation Ind Yes
Axial Recent Year 2008
Circ Wave Recent Year 2011
Geometry Recent Year 2007
Other Recent Year 2011
Has Hydrtst Conduc Before Ind No
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Preparer Name N*** J****
Preparer Title Regulatory Compliance Coordinator
Preparer Email N*********@o****.com
Preparer Telephone 580-395-6304
Preparer Fax 580-395-2933
Prepared Date 2016-10-14 00:00:00
Authorizer Name N*** J****
Authorizer Telephone 580-395-6304
Authorizer Title Regulatory Compliance Coordinator
Authorizer Email N*********@o****.com
Narrative As a result of an inline inspection (ili) on feb 12, 2012, this seam weld anomaly was selected for a direct examination and evaluation. The feature at this site was predicted to be 16% wall loss. Because the anomaly was located inside a casing, a project was put in place to cut out the anomaly and replace the section with new pipe, and with evaluation of the anomaly to be performed after the replacement was completed. On october 31, 2012, the area operations employee visited the proposed dig site at wolf road pipeline crossing to evaluate the scope of work for the upcoming anomaly investigation. While on site, the employee identified staining on the vent pipe and did a lel test, which tested positive for hydrocarbons. Initial samples were gathered by siphoning a sample from the vent pipe and analyzed by a third party. The analysis identified characteristics consistent with naptha, which was not a product being transported by that pipeline. With this information, oneok proceeded with the preparation for the anomaly excavation. On nov. 1, the pipeline was shutdown at approximately 1:00 a.M. And purged with nitrogen to allow the removal of the pipe in that casing and evaluate the anomaly. Although oneok did not believe at the time that there had been a release from its pipeline, the contaminated soil from the excavation was loaded into roll-off containers and sent to a disposal site. On nov. 3-4, the pipeline section containing the anomaly was removed from casing and new pipe installed through the existing casing. The pipeline was returned to service at 12:00 p.M. On nov. 4. A third party contractor was retained to remove the asbestos coating from the cut-out section, which was completed on nov. 5. On nov. 6, oneok's contract inspector arrived and completed nde of the anomaly. The contractor determined the defect was through-wall and not 16% wall loss, as had been indicated in the ili report. Based on this new information, the lab analysis was re-evaluated on nov. 7, and it was determined that the characteristics were similar enough to the oneok product in the pipeline to consider it a match. On nov. 8, the oneok environmental group notified the oneok compliance group that costs to remove and dispose of the contaminated soil would exceed $50,000. Based on this information, along with the evaluation identifying the through-wall crack in the removed section, oneok immediately made a report to nrc. The pipe samples were submitted to kiefner & associates for metallurgical analysis. The analysis determined a mill-related lack of fusion in the seam weld as root cause.

All rights reserved. Copyright © by ClearPHMSA