Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2012-06-25 — TX
Operator
Rose Rock Midstream L.p.
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$200
Incident datetime
2012-06-25 16:04
Report number
Location
TX
Narrative
A bolt in the victaulic coupling on the pump pulsation stabilizer failed, allowing the coupling to come loose and oil to escape from the top of the pulsation stabilizer. The controller noticed an increase in the flow rate from this pump station, shut down the pump and contacted field personnel to investigate. The field technician arrived on location, verified that the pulsation stabilizer was leaking and closed the appropriate valves to isolate the pulsation stabilizer and stop the flow of oil. All oil was contained on company property with the bulk of the oil contained inside the tank dike. Tank trucks were called in to pick up the oil and pump the recovered oil back into an isolated storage tank. All 5 victaulic couplings on pulsation stabilizers in the rose rock system were replaced with new couplings from the factory. Approximately 45 cubic yards of soil was remediated on- site and, after testing and with approval from the kansas department of health and environment, installed to its original location.
Detailed record list
Report Received Date
2012-07-19 00:00:00
Iyear
2012
Report Number
20120218
Supplemental Number
17758
Report Type
Supplemental Final
Operator Id
31476
Name
Rose Rock Midstream L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2012-06-25 16:04:00
Location Latitude
37.80389
Location Longitude
-96.51428
Commodity Released Type
Crude Oil
Unintentional Release Bbls
142
Intentional Release Bbls
0
Recovered Bbls
140
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Controller
Operator Type
Operator Employee
Incident Identified Datetime
2012-06-25 16:04:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2012-06-25 16:04:00
Restart Datetime
2012-06-26 10:59:00
On Site Datetime
2012-06-25 17:00:00
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Dickinson Station
Segment Name
Dickinson Station
Onshore State Abbreviation
Ks
Onshore Postal Code
67045
Onshore City Name
Reece
Onshore County Name
Greenwood
Designated Location
Survey Station No.
Designated Name
63+50
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Other
Item Involved Details
Pulsation Dampner/surge Chamber
Installation Year
2002
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Connection Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
200
Est Cost Prop Damage
200
Est Cost Emergency
1500
Est Cost Environmental
5000
Est Cost Other
0
Prpty
6900
Accident Psig
223
Mop Psig
280
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Pump Or Pump-Related Equipment
Eq Failure Type
Pump Or Pump-Related Equipment
Other Pump Ind
Appurtenance Failure
Additional Defect Ind
Yes
Preparer Name
E**** C***
Preparer Title
Director Corporate Ehs
Preparer Email
E****@s***********.com
Preparer Telephone
9186403394
Preparer Fax
9185247243
Prepared Date
2013-04-03 00:00:00
Authorizer Name
E**** C***
Authorizer Telephone
9186403384
Authorizer Title
Director Corporate Ehs
Authorizer Email
E****@s***********.com
Narrative
A bolt in the victaulic coupling on the pump pulsation stabilizer failed, allowing the coupling to come loose and oil to escape from the top of the pulsation stabilizer. The controller noticed an increase in the flow rate from this pump station, shut down the pump and contacted field personnel to investigate. The field technician arrived on location, verified that the pulsation stabilizer was leaking and closed the appropriate valves to isolate the pulsation stabilizer and stop the flow of oil. All oil was contained on company property with the bulk of the oil contained inside the tank dike. Tank trucks were called in to pick up the oil and pump the recovered oil back into an isolated storage tank. All 5 victaulic couplings on pulsation stabilizers in the rose rock system were replaced with new couplings from the factory. Approximately 45 cubic yards of soil was remediated on- site and, after testing and with approval from the kansas department of health and environment, installed to its original location.
| Report Received Date | 2012-07-19 00:00:00 |
|---|---|
| Iyear | 2012 |
| Report Number | 20120218 |
| Supplemental Number | 17758 |
| Report Type | Supplemental Final |
| Operator Id | 31476 PHMSA Enforcement |
| Name | Rose Rock Midstream L.p. |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2012-06-25 16:04:00 |
| Location Latitude | 37.80389 Google Maps OpenStreetMap |
| Location Longitude | -96.51428 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 142 |
| Intentional Release Bbls | 0 |
| Recovered Bbls | 140 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Controller |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2012-06-25 16:04:00 |
| System Part Involved | Onshore Pump/meter Station Equipment And Piping |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2012-06-25 16:04:00 |
| Restart Datetime | 2012-06-26 10:59:00 |
| On Site Datetime | 2012-06-25 17:00:00 |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Dickinson Station |
| Segment Name | Dickinson Station |
| Onshore State Abbreviation | Ks |
| Onshore Postal Code | 67045 |
| Onshore City Name | Reece |
| Onshore County Name | Greenwood |
| Designated Location | Survey Station No. |
| Designated Name | 63+50 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Other |
| Item Involved Details | Pulsation Dampner/surge Chamber |
| Installation Year | 2002 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Connection Failure |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 200 |
| Est Cost Prop Damage | 200 |
| Est Cost Emergency | 1500 |
| Est Cost Environmental | 5000 |
| Est Cost Other | 0 |
| Prpty | 6900 |
| Accident Psig | 223 |
| Mop Psig | 280 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | < 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Cpm In Place Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Pump Or Pump-Related Equipment |
| Eq Failure Type | Pump Or Pump-Related Equipment |
| Other Pump Ind | Appurtenance Failure |
| Additional Defect Ind | Yes |
| Preparer Name | E**** C*** |
| Preparer Title | Director Corporate Ehs |
| Preparer Email | E****@s***********.com |
| Preparer Telephone | 9186403394 |
| Preparer Fax | 9185247243 |
| Prepared Date | 2013-04-03 00:00:00 |
| Authorizer Name | E**** C*** |
| Authorizer Telephone | 9186403384 |
| Authorizer Title | Director Corporate Ehs |
| Authorizer Email | E****@s***********.com |
| Narrative | A bolt in the victaulic coupling on the pump pulsation stabilizer failed, allowing the coupling to come loose and oil to escape from the top of the pulsation stabilizer. The controller noticed an increase in the flow rate from this pump station, shut down the pump and contacted field personnel to investigate. The field technician arrived on location, verified that the pulsation stabilizer was leaking and closed the appropriate valves to isolate the pulsation stabilizer and stop the flow of oil. All oil was contained on company property with the bulk of the oil contained inside the tank dike. Tank trucks were called in to pick up the oil and pump the recovered oil back into an isolated storage tank. All 5 victaulic couplings on pulsation stabilizers in the rose rock system were replaced with new couplings from the factory. Approximately 45 cubic yards of soil was remediated on- site and, after testing and with approval from the kansas department of health and environment, installed to its original location. |