HL incident on 2012-04-10 — TX

Operator
Exxonmobil Pipeline Co
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$40,000
Incident datetime
2012-04-10 17:17
Report number
Location
TX
Narrative
Operator employee investigated station after smelling crude and discovered fresh crude oil in a previously excavated hole near the mainline p-2 suction valve. The station was shut down by a power surge at the time of discovery. An estimated 5.5 bbls. Of crude oil was released to soil from two internal corrosion pits in a valve body drain connection pipe at the st. James-north pump station. The release was discovered and reported to empco supervision by an empco employee on 4/10/12 at 5:17 pm after an unexpected commercial power failure which shut down the pump station. The northline pipeline and st. James-north pump station was immediately isolated and emergency response personnel and equipment were mobilized to the site. Agency notifications were made. The entire crude oil release was contained within empco station and oil reclaimed via vacuum truck within 3 hours of the release discovery. A review of scada system pipeline surveillance data (level 1) did not indicate any abnormal conditions due to the presumed slow release rate. Suspected internal corrosion was discovered in a valve body bleed pipe detail. The reconditioned valve was installed in 2003 as part of a project to construct the pump station. The valve was removed and blind flange installed to enable re-commissioning of the pipeline using an adjacent similar pump unit. Drain piping of three identical pump station isolation valves were pressure tested prior to station re-commissioning. A loss investigation is in-progress and mitigation strategies are being developed to quickly address three similar remaining valves in the pump station. The original nrc report # 1008304 showed the release amount to be 11 bbls. That volume was determined to be incorrect; the correct volume was determined by the amount recovered in the vacuum truck. Procedures were revised to periodically drain the valve to discourage development of conditions that can possibly lead to valve damage or impair the operation of the valve.
Detailed record list
Report Received Date
2012-05-09 00:00:00
Iyear
2012
Report Number
20120145
Supplemental Number
18341
Report Type
Supplemental Final
Operator Id
Name
Exxonmobil Pipeline Co
Operator Street Address
22777 Springwoods Village Parkway E2.2b-Emp
Operator City Name
Spring
Operator State Abbreviation
TX
Operator Postal Code
77389
Local Datetime
2012-04-10 17:17:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
5.5
Intentional Release Bbls
0
Recovered Bbls
5.5
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2012-04-10 17:17:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2012-04-10 17:17:00
Restart Datetime
2012-04-11 16:00:00
On Site Datetime
2012-04-10 17:25:00
Nrc Rpt Datetime
2012-04-10 18:40:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Automatic
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
0
Pipe Fac Name
St James Station North
Segment Name
St James To Anchorage Terminal
Onshore State Abbreviation
La
Onshore Postal Code
70086
Onshore City Name
St. James
Onshore County Name
St. James
Designated Location
Milepost/valve Station
Designated Name
00+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Excavation
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Valve
Valve Type
Auxiliary Or Other Valve
Installation Year
2003
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Internal Corrosion In The Pump's Suction Valve's Drain Line.
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
100
Est Cost Prop Damage
40000
Est Cost Emergency
1500
Est Cost Environmental
40000
Est Cost Other
0
Prpty
81600
Accident Psig
150
Mop Psig
1117
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
15
Internal Inspection Ind
No
Other Restrictions Ind
Yes
Operation Complications Ind
Yes
Other Complications Ind
Yes
Inspect Comp Details
Suction Side Of Pump
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Failed pump suction valve
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Localized Pitting
Int Microbiological Ind
Yes
Int Field Exam Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
Yes
Corrosion Lining
No
Cleaning Dewatering
Not Applicable - Not Mainline Pipe
Corrosion Coupons
Not Applicable - Not Mainline Pipe
Preparer Name
K***** L Y****
Preparer Title
Pipeline Safety Compliance Advisor
Preparer Email
K*************@e*********.com
Preparer Telephone
337-269-5221
Preparer Fax
337-662-5950
Prepared Date
2012-05-09 00:00:00
Authorizer Name
G*** W H*******
Authorizer Telephone
713-656-0227
Authorizer Title
Ess And H Manager
Authorizer Email
G**************@e*********.com
Narrative
Operator employee investigated station after smelling crude and discovered fresh crude oil in a previously excavated hole near the mainline p-2 suction valve. The station was shut down by a power surge at the time of discovery. An estimated 5.5 bbls. Of crude oil was released to soil from two internal corrosion pits in a valve body drain connection pipe at the st. James-north pump station. The release was discovered and reported to empco supervision by an empco employee on 4/10/12 at 5:17 pm after an unexpected commercial power failure which shut down the pump station. The northline pipeline and st. James-north pump station was immediately isolated and emergency response personnel and equipment were mobilized to the site. Agency notifications were made. The entire crude oil release was contained within empco station and oil reclaimed via vacuum truck within 3 hours of the release discovery. A review of scada system pipeline surveillance data (level 1) did not indicate any abnormal conditions due to the presumed slow release rate. Suspected internal corrosion was discovered in a valve body bleed pipe detail. The reconditioned valve was installed in 2003 as part of a project to construct the pump station. The valve was removed and blind flange installed to enable re-commissioning of the pipeline using an adjacent similar pump unit. Drain piping of three identical pump station isolation valves were pressure tested prior to station re-commissioning. A loss investigation is in-progress and mitigation strategies are being developed to quickly address three similar remaining valves in the pump station. The original nrc report # 1008304 showed the release amount to be 11 bbls. That volume was determined to be incorrect; the correct volume was determined by the amount recovered in the vacuum truck. Procedures were revised to periodically drain the valve to discourage development of conditions that can possibly lead to valve damage or impair the operation of the valve.
Report Received Date 2012-05-09 00:00:00
Iyear 2012
Report Number 20120145
Supplemental Number 18341
Report Type Supplemental Final
Operator Id 4906 PHMSA Enforcement
Name Exxonmobil Pipeline Co
Operator Street Address 22777 Springwoods Village Parkway E2.2b-Emp
Operator City Name Spring
Operator State Abbreviation TX
Operator Postal Code 77389
Local Datetime 2012-04-10 17:17:00
Location Latitude 30.010536 Google Maps OpenStreetMap
Location Longitude -90.861846 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 5.5
Intentional Release Bbls 0
Recovered Bbls 5.5
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2012-04-10 17:17:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2012-04-10 17:17:00
Restart Datetime 2012-04-11 16:00:00
On Site Datetime 2012-04-10 17:25:00
Nrc Rpt Datetime 2012-04-10 18:40:00
Nrc Rpt Num 1008304 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Automatic
Downstream Valve Type Ind Automatic
Num Pub Evacuated 0
Pipe Fac Name St James Station North
Segment Name St James To Anchorage Terminal
Onshore State Abbreviation La
Onshore Postal Code 70086
Onshore City Name St. James
Onshore County Name St. James
Designated Location Milepost/valve Station
Designated Name 00+00
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Exposed Due To Excavation
Crossing No
Pipe Facility Type Interstate
Item Involved Valve
Valve Type Auxiliary Or Other Valve
Installation Year 2003
Material Involved Carbon Steel
Release Type Other
Release Type Details Internal Corrosion In The Pump's Suction Valve's Drain Line.
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment Yes
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Usa Drinking Ind Yes
Usa Drinking Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 100
Est Cost Prop Damage 40000
Est Cost Emergency 1500
Est Cost Environmental 40000
Est Cost Other 0
Prpty 81600
Accident Psig 150
Mop Psig 1117
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 15
Internal Inspection Ind No
Other Restrictions Ind Yes
Operation Complications Ind Yes
Other Complications Ind Yes
Inspect Comp Details Suction Side Of Pump
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Failed pump suction valve
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details Internal Corrosion
Internal External Internal Corrosion
Int Visual Exam Results Localized Pitting
Int Microbiological Ind Yes
Int Field Exam Basis Ind Yes
Int Low Point Pipe Loc Ind Yes
Corrosion Inhibitors Yes
Corrosion Lining No
Cleaning Dewatering Not Applicable - Not Mainline Pipe
Corrosion Coupons Not Applicable - Not Mainline Pipe
Preparer Name K***** L Y****
Preparer Title Pipeline Safety Compliance Advisor
Preparer Email K*************@e*********.com
Preparer Telephone 337-269-5221
Preparer Fax 337-662-5950
Prepared Date 2012-05-09 00:00:00
Authorizer Name G*** W H*******
Authorizer Telephone 713-656-0227
Authorizer Title Ess And H Manager
Authorizer Email G**************@e*********.com
Narrative Operator employee investigated station after smelling crude and discovered fresh crude oil in a previously excavated hole near the mainline p-2 suction valve. The station was shut down by a power surge at the time of discovery. An estimated 5.5 bbls. Of crude oil was released to soil from two internal corrosion pits in a valve body drain connection pipe at the st. James-north pump station. The release was discovered and reported to empco supervision by an empco employee on 4/10/12 at 5:17 pm after an unexpected commercial power failure which shut down the pump station. The northline pipeline and st. James-north pump station was immediately isolated and emergency response personnel and equipment were mobilized to the site. Agency notifications were made. The entire crude oil release was contained within empco station and oil reclaimed via vacuum truck within 3 hours of the release discovery. A review of scada system pipeline surveillance data (level 1) did not indicate any abnormal conditions due to the presumed slow release rate. Suspected internal corrosion was discovered in a valve body bleed pipe detail. The reconditioned valve was installed in 2003 as part of a project to construct the pump station. The valve was removed and blind flange installed to enable re-commissioning of the pipeline using an adjacent similar pump unit. Drain piping of three identical pump station isolation valves were pressure tested prior to station re-commissioning. A loss investigation is in-progress and mitigation strategies are being developed to quickly address three similar remaining valves in the pump station. The original nrc report # 1008304 showed the release amount to be 11 bbls. That volume was determined to be incorrect; the correct volume was determined by the amount recovered in the vacuum truck. Procedures were revised to periodically drain the valve to discourage development of conditions that can possibly lead to valve damage or impair the operation of the valve.

All rights reserved. Copyright © by ClearPHMSA