GTG incident on 2012-11-14 — NY

Operator
Consolidated Edison Co Of New York
Cause
Equipment Failure
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$120,000
Incident datetime
2012-11-14 13:12
Report number
Location
NY
Narrative
On november 14, 2012 at 13:12 hrs. Gas construction reported a possible leak on the 24" steel transmission main at 23 maple street, eastchester, ny to the gas emergency response center (gerc). Two repairs were previously made on a parallel 4" high pressure 1932 steel distribution main and the gas readings indicated a possible leak on the transmission main. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), the emergency response group (erg) and supervision.Gas engineering, pressure control and gas control were notified. Gerc and gas control identified rov 25934 and mv 25968 to isolate the area per contingency case 34a. Gas control confirmed communication with rov 25934 and gds inspected and confirmed accessibility and position of mv 27235 (open) and mv # 36697 (closed). These valves are straddle connections to regulator station gr-425 (transmission-high pressure) and were needed for main depressurization and isolation as required. The leak was staffed overnight and an operational plan was developed. At 09:53 on november 15, 2012 the isolation of this segment of transmission main was confirmed. Pressure control was on location and the segment was depressurized via gr-425 and excavation commenced to expose the source of the leak. Gas control declared a condition yellow and issued a limited work order on the 245 psi transmission system to ensure system supply. Corrosion control performed a patrol over this system to ensure no unregistered activity is ongoing that would jeopardize the gas transmission system. Around-the-clock operations continued and on friday, november 15, 2012 at 19:15 hrs a confirmed visual leak on a 24" coupling approximately 20' south of the service supplying # 20 maple st (te). A welded repair sleeve was installed, and the associated testing was successful. The affected segment of main was re-energized and during the incremental pressure increase and associated leak surveillance, a second leak was detected over a coupling approximately 40' south of the original repair. The main was depressurized and a welded repair sleeve was successfully installed and tested. The main was re-energized and no other leaks found. Bronx construction-capital, westchester gas operations, pressure control and transmission engineering-major projects were on location. The transmission system was returned to normal operating conditions on sunday november 18, 2012 at 11:12 hrs. The US DOT, nys psc and tefd were notified. The tefd and psc visited the location and were kept apprised. Media relations was updated due to an inquiry from bloomberg news. There were no evacuations or injuries attributed to this incident.This was a serious level incident.
Detailed record list
Report Received Date
2012-12-10 00:00:00
Iyear
2012
Report Number
20120120
Supplemental Number
15814
Report Type
Supplemental Final
Operator Id
Name
Consolidated Edison Co Of New York
Operator Street Address
4 Irving Place
Operator City Name
New York
Operator State Abbreviation
NY
Operator Postal Code
10003
Local Datetime
2012-11-14 13:12:00
Location Latitude
Location Longitude
Nrc Rpt Num
Nrc Rpt Datetime
2012-11-15 10:16:00
Commodity Released Type
Natural Gas
Unintentional Release
11
Intentional Release
0
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2012-11-15 09:53:00
Restart Datetime
2012-11-18 11:12:00
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Incident Identified Datetime
2012-11-14 13:12:00
On Site Datetime
2012-11-14 13:12:00
On Off Shore
Onshore
Onshore State Abbreviation
Ny
Onshore Postal Code
10707-0000
Onshore City Name
Eastchester
Onshore County Name
Westchester
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Intrastate
System Part Involved
Onshore Pipeline, Including Valve Sites
Item Involved
Other
Item Involved Details
(2) 24" Compression Couplings
Installation Year
1948
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Seal Or Packing
Class Location Type
Class 4 Location
Could Be Hca
Yes
Determination Method
Method1
Pir Radius
259
Heat Damage Ind
No
Non Heat Damage Ind
No
Hca Fatalities Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
22
Est Cost Intentional Release
0
Est Cost Prop Damage
120000
Est Cost Emergency
2500
Est Cost Other
0
Prpty
122522
Accident Psig
209
Mop Psig
245
Mop Cfr Section
Not On Omb-Approved Form When Submitted
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Remotely Controlled
Length Segment Isolated
6566
Internal Inspection Ind
No
Diameter Change Ind
Yes
Unsuitable Mainline Ind
Yes
Tight Mitered Ind
Yes
Operation Complications Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
No
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Minor leak on compression couplings resulting in no pressure loss or increased flow.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Threaded Connection/coupling Failure
Eq Failure Type
Threaded Connection/coupling Failure
Other Stripped Ind
Mechanical Coupling
Eq Additional Other Ind
Yes
Eq Additional Other Details
Compression Coupling Leak At Seal
Preparer Name
K**** F****
Preparer Title
Operations Manager--Gas Emergency Response Center
Preparer Email
F*****@c****.com
Preparer Telephone
718-319-2310
Preparer Fax
718-904-4607
Authorizer Name
V***** D******
Authorizer Title
Deptartment Manager--Gas Emergency Response Center
Authorizer Telephone
718-319-2350
Authorizer Email
D*******@c****.com
Narrative
On november 14, 2012 at 13:12 hrs. Gas construction reported a possible leak on the 24" steel transmission main at 23 maple street, eastchester, ny to the gas emergency response center (gerc). Two repairs were previously made on a parallel 4" high pressure 1932 steel distribution main and the gas readings indicated a possible leak on the transmission main. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), the emergency response group (erg) and supervision.Gas engineering, pressure control and gas control were notified. Gerc and gas control identified rov 25934 and mv 25968 to isolate the area per contingency case 34a. Gas control confirmed communication with rov 25934 and gds inspected and confirmed accessibility and position of mv 27235 (open) and mv # 36697 (closed). These valves are straddle connections to regulator station gr-425 (transmission-high pressure) and were needed for main depressurization and isolation as required. The leak was staffed overnight and an operational plan was developed. At 09:53 on november 15, 2012 the isolation of this segment of transmission main was confirmed. Pressure control was on location and the segment was depressurized via gr-425 and excavation commenced to expose the source of the leak. Gas control declared a condition yellow and issued a limited work order on the 245 psi transmission system to ensure system supply. Corrosion control performed a patrol over this system to ensure no unregistered activity is ongoing that would jeopardize the gas transmission system. Around-the-clock operations continued and on friday, november 15, 2012 at 19:15 hrs a confirmed visual leak on a 24" coupling approximately 20' south of the service supplying # 20 maple st (te). A welded repair sleeve was installed, and the associated testing was successful. The affected segment of main was re-energized and during the incremental pressure increase and associated leak surveillance, a second leak was detected over a coupling approximately 40' south of the original repair. The main was depressurized and a welded repair sleeve was successfully installed and tested. The main was re-energized and no other leaks found. Bronx construction-capital, westchester gas operations, pressure control and transmission engineering-major projects were on location. The transmission system was returned to normal operating conditions on sunday november 18, 2012 at 11:12 hrs. The US DOT, nys psc and tefd were notified. The tefd and psc visited the location and were kept apprised. Media relations was updated due to an inquiry from bloomberg news. There were no evacuations or injuries attributed to this incident.This was a serious level incident.
Report Received Date 2012-12-10 00:00:00
Iyear 2012
Report Number 20120120
Supplemental Number 15814
Report Type Supplemental Final
Operator Id 2704 PHMSA Enforcement
Name Consolidated Edison Co Of New York
Operator Street Address 4 Irving Place
Operator City Name New York
Operator State Abbreviation NY
Operator Postal Code 10003
Local Datetime 2012-11-14 13:12:00
Location Latitude 40.976441 Google Maps OpenStreetMap
Location Longitude -73.807641 Google Maps OpenStreetMap
Nrc Rpt Num 1030677 NRC Report How to search
Nrc Rpt Datetime 2012-11-15 10:16:00
Commodity Released Type Natural Gas
Unintentional Release 11
Intentional Release 0
Accompanying Liquid 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Shutdown Due Accident Ind Yes
Shutdown Datetime 2012-11-15 09:53:00
Restart Datetime 2012-11-18 11:12:00
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Incident Identified Datetime 2012-11-14 13:12:00
On Site Datetime 2012-11-14 13:12:00
On Off Shore Onshore
Onshore State Abbreviation Ny
Onshore Postal Code 10707-0000
Onshore City Name Eastchester
Onshore County Name Westchester
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Pavement
Depth Of Cover 48
Crossing No
Pipe Facility Type Intrastate
System Part Involved Onshore Pipeline, Including Valve Sites
Item Involved Other
Item Involved Details (2) 24" Compression Couplings
Installation Year 1948
Material Involved Carbon Steel
Release Type Leak
Leak Type Seal Or Packing
Class Location Type Class 4 Location
Could Be Hca Yes
Determination Method Method1
Pir Radius 259
Heat Damage Ind No
Non Heat Damage Ind No
Hca Fatalities Ind No
Est Cost Oper Paid 0
Est Cost Unintentional Release 22
Est Cost Intentional Release 0
Est Cost Prop Damage 120000
Est Cost Emergency 2500
Est Cost Other 0
Prpty 122522
Accident Psig 209
Mop Psig 245
Mop Cfr Section Not On Omb-Approved Form When Submitted View CFR 49 §192
Accident Pressure Pressure Did Not Exceed Maop
Pressure Restriction Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Remotely Controlled
Length Segment Isolated 6566
Internal Inspection Ind No
Diameter Change Ind Yes
Unsuitable Mainline Ind Yes
Tight Mitered Ind Yes
Operation Complications Ind No
Pipeline Function Transmission System
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind No
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Minor leak on compression couplings resulting in no pressure loss or increased flow.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Threaded Connection/coupling Failure
Eq Failure Type Threaded Connection/coupling Failure
Other Stripped Ind Mechanical Coupling
Eq Additional Other Ind Yes
Eq Additional Other Details Compression Coupling Leak At Seal
Preparer Name K**** F****
Preparer Title Operations Manager--Gas Emergency Response Center
Preparer Email F*****@c****.com
Preparer Telephone 718-319-2310
Preparer Fax 718-904-4607
Authorizer Name V***** D******
Authorizer Title Deptartment Manager--Gas Emergency Response Center
Authorizer Telephone 718-319-2350
Authorizer Email D*******@c****.com
Narrative On november 14, 2012 at 13:12 hrs. Gas construction reported a possible leak on the 24" steel transmission main at 23 maple street, eastchester, ny to the gas emergency response center (gerc). Two repairs were previously made on a parallel 4" high pressure 1932 steel distribution main and the gas readings indicated a possible leak on the transmission main. A code murre (multiple resource response event) was initiated and the gerc dispatched gas distribution services (gds), the emergency response group (erg) and supervision.Gas engineering, pressure control and gas control were notified. Gerc and gas control identified rov 25934 and mv 25968 to isolate the area per contingency case 34a. Gas control confirmed communication with rov 25934 and gds inspected and confirmed accessibility and position of mv 27235 (open) and mv # 36697 (closed). These valves are straddle connections to regulator station gr-425 (transmission-high pressure) and were needed for main depressurization and isolation as required. The leak was staffed overnight and an operational plan was developed. At 09:53 on november 15, 2012 the isolation of this segment of transmission main was confirmed. Pressure control was on location and the segment was depressurized via gr-425 and excavation commenced to expose the source of the leak. Gas control declared a condition yellow and issued a limited work order on the 245 psi transmission system to ensure system supply. Corrosion control performed a patrol over this system to ensure no unregistered activity is ongoing that would jeopardize the gas transmission system. Around-the-clock operations continued and on friday, november 15, 2012 at 19:15 hrs a confirmed visual leak on a 24" coupling approximately 20' south of the service supplying # 20 maple st (te). A welded repair sleeve was installed, and the associated testing was successful. The affected segment of main was re-energized and during the incremental pressure increase and associated leak surveillance, a second leak was detected over a coupling approximately 40' south of the original repair. The main was depressurized and a welded repair sleeve was successfully installed and tested. The main was re-energized and no other leaks found. Bronx construction-capital, westchester gas operations, pressure control and transmission engineering-major projects were on location. The transmission system was returned to normal operating conditions on sunday november 18, 2012 at 11:12 hrs. The US DOT, nys psc and tefd were notified. The tefd and psc visited the location and were kept apprised. Media relations was updated due to an inquiry from bloomberg news. There were no evacuations or injuries attributed to this incident.This was a serious level incident.

All rights reserved. Copyright © by ClearPHMSA