GD incident on 2011-07-17 — VA

Operator
Richmond, City Of
Cause
Other Outside Force Damage
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$126
Incident datetime
2011-07-17 04:50
Report number
Location
VA
Narrative
This is a follow-up to the telephone call placed on 7/7/11. Incident report #982932, which occurred at 1413 bowen street, richmond, va. The incident was reported to the national response center at 06:40 on sunday, 7/7/11. A fire, unrelated to natural gas, was the primary cause of the incident. The total damage is estimated to be more than $50,000. The origin of the fire has not been determined, but the fire dept. Has ruled that was not the initiating cause of the event. The city of richmond performed a series of tests which included a leak survey of the outer perimeter of the building, bar hole test, and a pressure test of the gas service. During the fire, the riser, regulator, and meter were destroyed, which caused a leak on the riser that showed up during the pressure test of the service. A test of the riser determined that the failure was due to the heat from the fire. Also, the city of richmond, department of public utilities, had an odorometer test performed by the supervisor of pressure control and found the odorant to be in the acceptable range.
Detailed record list
Occurred At
2011-07-17 04:50:00
Year
2011
Report Received Date
2011-08-02 00:00:00
Iyear
2011.0
Report Number
20110263.0
Supplemental Number
15289.0
Report Type
Original
Operator Id
Name
Richmond, City Of
Operator Street Address
730 East Broad Street
Operator City Name
Richmond
Operator State Abbreviation
VA
Operator Postal Code
23219
Local Datetime
2011-07-17 04:50:00
Location Street Address
1413 Bowen Street
Location City Name
Richmond
Location State Abbreviation
VA
Location Postal Code
23219
Location Latitude
Location Longitude
Nrc Rpt Datetime
2011-07-17 06:40:00
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
6.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0.0
Incident Identified Datetime
2011-07-17 04:50:00
On Site Datetime
2011-07-17 05:11:00
Federal
No
Location Type
Private Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
20.0
Crossing
No
Pipe Facility Type
Municipally Owned
System Part Involved
Service
Installation Year
2004.0
Pipe Diameter
1.0
Pipe Specification
D2513
Pipe Manufacturer
Yellowstripe
Material Involved
Plastic
Plastic Type
Polyethylene (Pe)
Material Pe Pipe Code
3408
Release Type
Rupture
Rupture Length
1
Rupture Width
1
Class Location Type
Class 3 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
126.0
Est Cost Emergency
600.0
Est Cost Other
0.0
Est Cost Unintentional Release
29.0
Prpty
755.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
1.0
Accident Psig
22.0
Normal Psig
22.0
Mop Psig
30.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
No
Accident Identifier
Notification From Emergency Responder
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Nearby Industrial, Man-Made, Or Other Fire/explosion As Primary Cause Of Incident
Outside Force Type
Nearby Industrial, Man-Made, Or Other Fire/explosion As Primary Cause Of Incident
Preparer Name
C*** V* J****
Preparer Title
Operations Manager - Gas Maintenance
Preparer Email
C*********@r**********.com
Preparer Telephone
804/646-8341
Preparer Fax
804/646-8399
Authorizer Name
C*** V* J****
Authorizer Title
Operations Manager - Gas Maintenance
Authorizer Telephone
804/646-8341
Authorizer Email
C*********@r**********.com
Narrative
This is a follow-up to the telephone call placed on 7/7/11. Incident report #982932, which occurred at 1413 bowen street, richmond, va. The incident was reported to the national response center at 06:40 on sunday, 7/7/11. A fire, unrelated to natural gas, was the primary cause of the incident. The total damage is estimated to be more than $50,000. The origin of the fire has not been determined, but the fire dept. Has ruled that was not the initiating cause of the event. The city of richmond performed a series of tests which included a leak survey of the outer perimeter of the building, bar hole test, and a pressure test of the gas service. During the fire, the riser, regulator, and meter were destroyed, which caused a leak on the riser that showed up during the pressure test of the service. A test of the riser determined that the failure was due to the heat from the fire. Also, the city of richmond, department of public utilities, had an odorometer test performed by the supervisor of pressure control and found the odorant to be in the acceptable range.
Occurred At 2011-07-17 04:50:00
Year 2011
Report Received Date 2011-08-02 00:00:00
Iyear 2011.0
Report Number 20110263.0
Supplemental Number 15289.0
Report Type Original
Operator Id 17360 PHMSA Enforcement
Name Richmond, City Of
Operator Street Address 730 East Broad Street
Operator City Name Richmond
Operator State Abbreviation VA
Operator Postal Code 23219
Local Datetime 2011-07-17 04:50:00
Location Street Address 1413 Bowen Street
Location City Name Richmond
Location State Abbreviation VA
Location Postal Code 23219
Location Latitude 37.3006 Google Maps OpenStreetMap
Location Longitude -77.2618 Google Maps OpenStreetMap
Nrc Rpt Datetime 2011-07-17 06:40:00
Nrc Rpt Num 982932 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 6.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0.0
Incident Identified Datetime 2011-07-17 04:50:00
On Site Datetime 2011-07-17 05:11:00
Federal No
Location Type Private Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 20.0
Crossing No
Pipe Facility Type Municipally Owned
System Part Involved Service
Installation Year 2004.0
Pipe Diameter 1.0
Pipe Specification D2513
Pipe Manufacturer Yellowstripe
Material Involved Plastic
Plastic Type Polyethylene (Pe)
Material Pe Pipe Code 3408
Release Type Rupture
Rupture Length 1
Rupture Width 1
Class Location Type Class 3 Location
Est Cost Oper Paid 0.0
Est Cost Prop Damage 126.0
Est Cost Emergency 600.0
Est Cost Other 0.0
Est Cost Unintentional Release 29.0
Prpty 755.0
Commercial Affected 0.0
Industrial Affected 0.0
Residences Affected 1.0
Accident Psig 22.0
Normal Psig 22.0
Mop Psig 30.0
Accident Pressure Pressure Did Not Exceed Maop
Scada In Place Ind No
Accident Identifier Notification From Emergency Responder
Investigation Status No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Other Outside Force Damage
Cause Details Nearby Industrial, Man-Made, Or Other Fire/explosion As Primary Cause Of Incident
Outside Force Type Nearby Industrial, Man-Made, Or Other Fire/explosion As Primary Cause Of Incident
Preparer Name C*** V* J****
Preparer Title Operations Manager - Gas Maintenance
Preparer Email C*********@r**********.com
Preparer Telephone 804/646-8341
Preparer Fax 804/646-8399
Authorizer Name C*** V* J****
Authorizer Title Operations Manager - Gas Maintenance
Authorizer Telephone 804/646-8341
Authorizer Email C*********@r**********.com
Narrative This is a follow-up to the telephone call placed on 7/7/11. Incident report #982932, which occurred at 1413 bowen street, richmond, va. The incident was reported to the national response center at 06:40 on sunday, 7/7/11. A fire, unrelated to natural gas, was the primary cause of the incident. The total damage is estimated to be more than $50,000. The origin of the fire has not been determined, but the fire dept. Has ruled that was not the initiating cause of the event. The city of richmond performed a series of tests which included a leak survey of the outer perimeter of the building, bar hole test, and a pressure test of the gas service. During the fire, the riser, regulator, and meter were destroyed, which caused a leak on the riser that showed up during the pressure test of the service. A test of the riser determined that the failure was due to the heat from the fire. Also, the city of richmond, department of public utilities, had an odorometer test performed by the supervisor of pressure control and found the odorant to be in the acceptable range.