HL incident on 2010-01-15 — CA

Operator
Pacific Pipeline System Llc
Cause
Other Outside Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$0
Incident datetime
2010-01-15 07:05
Report number
Location
CA
Narrative
This release occured when the valve (2750) was opened during the process of making a crude oil delivery. It is thought that during construction acitivities at the tank farm facility a third party contractor broke the drain line on the valve body while performing construction work and when the operator opened the valve to make a delivery it resulted in the release. The release was contained to the ground within the tank farm and properly cleaned up. Supplemental narrative: this supplemental report is submitted at the request of PHMSA to more specifically report the cause of the accident. The cause reported in this supplemental report under g4 more accurately states the cause.
Detailed record list
Report Received Date
2011-03-10 00:00:00
Iyear
2010
Report Number
20110083
Supplemental Number
17836
Report Type
Supplemental Final
Operator Id
Name
Pacific Pipeline System Llc
Operator Street Address
5900 Cherry Ave
Operator City Name
Long Beach
Operator State Abbreviation
CA
Operator Postal Code
90805
Local Datetime
2010-01-15 07:05:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
1
Intentional Release Bbls
0
Recovered Bbls
1
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Contractor Working For The Operator
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Ignite Ind
No
Explode Ind
No
Pipe Fac Name
Line 63 South Pacific Pipelines Bp Refinery Tank F
Onshore State Abbreviation
Ca
Onshore Postal Code
90749
Onshore City Name
Carson
Onshore County Name
Los Angeles
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Other
Incident Area Details
Valve Drain Line
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Other
Item Involved Details
Valve Drain Line
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Third Party Damage To Valve Drain Line
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
75000
Est Cost Prop Damage
0
Est Cost Emergency
1000000
Est Cost Environmental
3500000
Est Cost Other
0
Prpty
4575000
Accident Psig
250
Mop Psig
600
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype
Third Party
Preparer Name
S***** N*****
Preparer Title
Compliance Specialist
Preparer Email
S******@p****.com
Preparer Telephone
7139935673
Preparer Fax
7136464310
Prepared Date
2013-04-08 00:00:00
Authorizer Name
J***** J****
Authorizer Telephone
7139935162
Authorizer Title
Sr Dir Of Env And Reg Compliance
Authorizer Email
J******@p****.com
Narrative
This release occured when the valve (2750) was opened during the process of making a crude oil delivery. It is thought that during construction acitivities at the tank farm facility a third party contractor broke the drain line on the valve body while performing construction work and when the operator opened the valve to make a delivery it resulted in the release. The release was contained to the ground within the tank farm and properly cleaned up. Supplemental narrative: this supplemental report is submitted at the request of PHMSA to more specifically report the cause of the accident. The cause reported in this supplemental report under g4 more accurately states the cause.
Report Received Date 2011-03-10 00:00:00
Iyear 2010
Report Number 20110083
Supplemental Number 17836
Report Type Supplemental Final
Operator Id 31325 PHMSA Enforcement
Name Pacific Pipeline System Llc
Operator Street Address 5900 Cherry Ave
Operator City Name Long Beach
Operator State Abbreviation CA
Operator Postal Code 90805
Local Datetime 2010-01-15 07:05:00
Location Latitude 33.80933 Google Maps OpenStreetMap
Location Longitude -118.25413 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 1
Intentional Release Bbls 0
Recovered Bbls 1
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Contractor Working For The Operator
System Part Involved Onshore Terminal/tank Farm Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind No
Ignite Ind No
Explode Ind No
Pipe Fac Name Line 63 South Pacific Pipelines Bp Refinery Tank F
Onshore State Abbreviation Ca
Onshore Postal Code 90749
Onshore City Name Carson
Onshore County Name Los Angeles
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Other
Incident Area Details Valve Drain Line
Crossing No
Pipe Facility Type Intrastate
Item Involved Other
Item Involved Details Valve Drain Line
Material Involved Carbon Steel
Release Type Other
Release Type Details Third Party Damage To Valve Drain Line
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 75000
Est Cost Prop Damage 0
Est Cost Emergency 1000000
Est Cost Environmental 3500000
Est Cost Other 0
Prpty 4575000
Accident Psig 250
Mop Psig 600
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Other Outside Force Damage
Cause Details Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype Third Party
Preparer Name S***** N*****
Preparer Title Compliance Specialist
Preparer Email S******@p****.com
Preparer Telephone 7139935673
Preparer Fax 7136464310
Prepared Date 2013-04-08 00:00:00
Authorizer Name J***** J****
Authorizer Telephone 7139935162
Authorizer Title Sr Dir Of Env And Reg Compliance
Authorizer Email J******@p****.com
Narrative This release occured when the valve (2750) was opened during the process of making a crude oil delivery. It is thought that during construction acitivities at the tank farm facility a third party contractor broke the drain line on the valve body while performing construction work and when the operator opened the valve to make a delivery it resulted in the release. The release was contained to the ground within the tank farm and properly cleaned up. Supplemental narrative: this supplemental report is submitted at the request of PHMSA to more specifically report the cause of the accident. The cause reported in this supplemental report under g4 more accurately states the cause.