Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2010-08-05 — OK
Operator
Magellan Pipeline Company, Lp
Cause
Notification Issue
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$80,000
Incident datetime
2010-08-05 19:38
Report number
Location
OK
Narrative
At 19:38 on 08/05/10, operations control has issued a code red for the #3-12' wynnewood to oklahoma city line just east of paoli oklahoma in garvin county. A code red was issued based on a drop in pressure and a third party call of product spraying out of the ground and it smelled like diesel. The pipeline in question was active at the time of the call. The pipeline, and any other affected pipelines were shutdown and isolated. At mp 15.0 a d-6 dozer was observed to be in close proximity to the line strike. There was also evidence of dirt work activity over and around our pipeline. Landowner was grading over the pipeline excavating dirt to build up his pond dike. Landowner did not make a one-call notification as he was exempt. The upstream pipeline marker was ~80' from the failure, the downstream marker was ~230' from the failure. The line was permantley repaired on 8/7/10 at ~6:00 a.M. Note: a post drug test was performed on the controller: 1 performed; 0 failed (online form has a glitch that will not allow this section to be filled out accurately, will not allow "0".)
Detailed record list
Report Received Date
2010-08-27 00:00:00
Iyear
2010
Report Number
20100183
Supplemental Number
19349
Report Type
Supplemental Final
Operator Id
22610
Name
Magellan Pipeline Company, Lp
Operator Street Address
100 West 5th Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2010-08-05 19:38:00
Location Latitude
34.82512
Location Longitude
-97.18992
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls
320
Intentional Release Bbls
0
Recovered Bbls
320
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime
2010-08-05 19:38:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2010-08-05 19:38:00
Restart Datetime
2010-08-07 08:55:00
On Site Datetime
2010-08-05 21:02:00
Nrc Rpt Datetime
2010-08-05 21:02:00
Nrc Rpt Num
950080
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Remotely Controlled
Num Pub Evacuated
0
Pipe Fac Name
Wynnewood To Okc
Segment Name
3-12 Line
Onshore State Abbreviation
Ok
Onshore Postal Code
73074
Onshore City Name
Paoli
Onshore County Name
Garvin
Designated Location
Milepost/valve Station
Designated Name
15
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Excavation
Depth Of Cover
54
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
12.75
Pipe Wall Thickness
0.203
Pipe Smys
65000
Pipe Specification
5l X65
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
California Steel
Pipe Coating Type
Fusion Bonded Epoxy(Fbe)
Installation Year
1998
Manufactured Year
1997
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
2
Puncture Circum
0.1
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Usa Drinking Ind
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
30300
Est Cost Prop Damage
80000
Est Cost Emergency
45000
Est Cost Environmental
85000
Est Cost Other
0
Prpty
240300
Accident Psig
906
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
353760
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Third party damage
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
1
Num Employees Failed
0
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
No
Notify Cga Dirt
No
Private Row Ind
Yes
Private Subtype
Private Landowner
Excavator Type
Occupant
Excavator Equipment
Grader/scraper
Work Performed
Grading
One Call Notified Ind
No
Locator Type
Unknown/other
Visible Marks
Unknown/other
Service Interruption
Yes
Service Interruption Hours
48
Root Cause Category
Notification Issue
Root Cause Type
No Notification Made To The One-Call Center/811
Preparer Name
D******* C*********
Preparer Title
Compliance Coordinator
Preparer Email
D******************@m*********.com
Preparer Telephone
918-574-7386
Preparer Fax
918-574-7246
Prepared Date
2014-05-01 00:00:00
Authorizer Name
D******* C*********
Authorizer Telephone
918-574-7386
Authorizer Title
Compliance Coordinator
Authorizer Email
D******************@m*********.com
Narrative
At 19:38 on 08/05/10, operations control has issued a code red for the #3-12' wynnewood to oklahoma city line just east of paoli oklahoma in garvin county. A code red was issued based on a drop in pressure and a third party call of product spraying out of the ground and it smelled like diesel. The pipeline in question was active at the time of the call. The pipeline, and any other affected pipelines were shutdown and isolated. At mp 15.0 a d-6 dozer was observed to be in close proximity to the line strike. There was also evidence of dirt work activity over and around our pipeline. Landowner was grading over the pipeline excavating dirt to build up his pond dike. Landowner did not make a one-call notification as he was exempt. The upstream pipeline marker was ~80' from the failure, the downstream marker was ~230' from the failure. The line was permantley repaired on 8/7/10 at ~6:00 a.M. Note: a post drug test was performed on the controller: 1 performed; 0 failed (online form has a glitch that will not allow this section to be filled out accurately, will not allow "0".)
| Report Received Date | 2010-08-27 00:00:00 |
|---|---|
| Iyear | 2010 |
| Report Number | 20100183 |
| Supplemental Number | 19349 |
| Report Type | Supplemental Final |
| Operator Id | 22610 PHMSA Enforcement |
| Name | Magellan Pipeline Company, Lp |
| Operator Street Address | 100 West 5th Street |
| Operator City Name | Tulsa |
| Operator State Abbreviation | OK |
| Operator Postal Code | 74103 |
| Local Datetime | 2010-08-05 19:38:00 |
| Location Latitude | 34.82512 Google Maps OpenStreetMap |
| Location Longitude | -97.18992 Google Maps OpenStreetMap |
| Commodity Released Type | Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions |
| Commodity Subtype | Diesel, Fuel Oil, Kerosene, Jet Fuel |
| Unintentional Release Bbls | 320 |
| Intentional Release Bbls | 0 |
| Recovered Bbls | 320 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations) |
| Incident Identified Datetime | 2010-08-05 19:38:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2010-08-05 19:38:00 |
| Restart Datetime | 2010-08-07 08:55:00 |
| On Site Datetime | 2010-08-05 21:02:00 |
| Nrc Rpt Datetime | 2010-08-05 21:02:00 |
| Nrc Rpt Num | 950080 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Remotely Controlled |
| Downstream Valve Type Ind | Remotely Controlled |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Wynnewood To Okc |
| Segment Name | 3-12 Line |
| Onshore State Abbreviation | Ok |
| Onshore Postal Code | 73074 |
| Onshore City Name | Paoli |
| Onshore County Name | Garvin |
| Designated Location | Milepost/valve Station |
| Designated Name | 15 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Exposed Due To Excavation |
| Depth Of Cover | 54 |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 12.75 |
| Pipe Wall Thickness | 0.203 |
| Pipe Smys | 65000 |
| Pipe Specification | 5l X65 |
| Pipe Seam Type | Erw - High Frequency |
| Pipe Manufacturer | California Steel |
| Pipe Coating Type | Fusion Bonded Epoxy(Fbe) |
| Installation Year | 1998 |
| Manufactured Year | 1997 |
| Material Involved | Carbon Steel |
| Release Type | Mechanical Puncture |
| Puncture Axial | 2 |
| Puncture Circum | 0.1 |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| Usa Drinking Ind | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 30300 |
| Est Cost Prop Damage | 80000 |
| Est Cost Emergency | 45000 |
| Est Cost Environmental | 85000 |
| Est Cost Other | 0 |
| Prpty | 240300 |
| Accident Psig | 906 |
| Mop Psig | 1440 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 353760 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Cpm In Place Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Third party damage |
| Employee Drug Test Ind | Yes |
| Contractor Drug Test Ind | No |
| Num Employees Tested | 1 |
| Num Employees Failed | 0 |
| Cause | Excavation Damage |
| Cause Details | Excavation Damage By Third Party |
| Ex Party Type | Excavation Damage By Third Party |
| Prior Notification Ind | No |
| Notify Cga Dirt | No |
| Private Row Ind | Yes |
| Private Subtype | Private Landowner |
| Excavator Type | Occupant |
| Excavator Equipment | Grader/scraper |
| Work Performed | Grading |
| One Call Notified Ind | No |
| Locator Type | Unknown/other |
| Visible Marks | Unknown/other |
| Service Interruption | Yes |
| Service Interruption Hours | 48 |
| Root Cause Category | Notification Issue |
| Root Cause Type | No Notification Made To The One-Call Center/811 |
| Preparer Name | D******* C********* |
| Preparer Title | Compliance Coordinator |
| Preparer Email | D******************@m*********.com |
| Preparer Telephone | 918-574-7386 |
| Preparer Fax | 918-574-7246 |
| Prepared Date | 2014-05-01 00:00:00 |
| Authorizer Name | D******* C********* |
| Authorizer Telephone | 918-574-7386 |
| Authorizer Title | Compliance Coordinator |
| Authorizer Email | D******************@m*********.com |
| Narrative | At 19:38 on 08/05/10, operations control has issued a code red for the #3-12' wynnewood to oklahoma city line just east of paoli oklahoma in garvin county. A code red was issued based on a drop in pressure and a third party call of product spraying out of the ground and it smelled like diesel. The pipeline in question was active at the time of the call. The pipeline, and any other affected pipelines were shutdown and isolated. At mp 15.0 a d-6 dozer was observed to be in close proximity to the line strike. There was also evidence of dirt work activity over and around our pipeline. Landowner was grading over the pipeline excavating dirt to build up his pond dike. Landowner did not make a one-call notification as he was exempt. The upstream pipeline marker was ~80' from the failure, the downstream marker was ~230' from the failure. The line was permantley repaired on 8/7/10 at ~6:00 a.M. Note: a post drug test was performed on the controller: 1 performed; 0 failed (online form has a glitch that will not allow this section to be filled out accurately, will not allow "0".) |