HL incident on 2010-07-05 — TX

Operator
Dixie Pipeline
Cause
Notification Issue
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
1 fatality 1 injury
Property damage (nominal)
$345,058
Incident datetime
2010-07-05 10:40
Report number
Location
TX
Narrative
On july 5, 2010, a private landowner was performing road work on his property adjacent to a pond and within the dixie pipeline designated row. The landowner did not contact one-call and did not contact dixie. The landowner hit the 8-inch dixie pipeline on his property with his dozer. A gouge and split from the dozer that penetrated through the wall of the pipeline resulted in a release of propane that led to a subsequent explosion and fire. The landowner, who was operating the dozer, was injured by the release. One fatality resulted from the subsequent explosion and fire with additional property damage ensuing. The operator took immediate action to isolate the pipeline and reduce the impact to the public and the environment.
Detailed record list
Report Received Date
2010-08-02 00:00:00
Iyear
2010
Report Number
20100163
Supplemental Number
16455
Report Type
Supplemental Final
Operator Id
Name
Dixie Pipeline
Operator Street Address
1100 Louisiana St.
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2010-07-05 10:40:00
Location Latitude
Location Longitude
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls
3104
Intentional Release Bbls
0
Recovered Bbls
0
Fatality Ind
Yes
Num Emp Fatalities
0
Num Contr Fatalities
0
Num Er Fatalities
0
Num Worker Fatalities
0
Num Gp Fatalities
1
Fatal
1
Injury Ind
Yes
Num Emp Injuries
0
Num Contr Injuries
0
Num Er Injuries
0
Num Worker Injuries
0
Num Gp Injuries
1
Injure
1
Accident Identifier
Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime
2010-07-05 10:40:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2010-07-05 10:52:00
Restart Datetime
2010-07-10 11:52:00
On Site Datetime
2010-07-05 12:27:00
Nrc Rpt Datetime
2010-07-05 11:58:00
Nrc Rpt Num
Ignite Ind
Yes
Explode Ind
Yes
Upstream Valve Type Ind
Automatic
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
1
Pipe Fac Name
Dixie Pipeline
Segment Name
120
Onshore State Abbreviation
Ga
Onshore Postal Code
30824
Onshore City Name
Thomson
Onshore County Name
Mcduffie
Designated Location
Milepost/valve Station
Designated Name
817.11
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
36
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8.625
Pipe Wall Thickness
0.188
Pipe Smys
52000
Pipe Specification
Api 5l
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Stupp Corp.
Pipe Coating Type
Coal Tar
Installation Year
1961
Manufactured Year
1961
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
4.9
Puncture Circum
9.4
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
130124
Est Cost Prop Damage
345058
Est Cost Emergency
49093
Est Cost Environmental
0
Est Cost Other
0
Prpty
524275
Accident Psig
847
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
292512
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Controller Ind
Yes
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
1
Num Employees Failed
0
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
No
Notify Cga Dirt
Yes
Pipeline Easement Row Ind
Yes
Excavator Type
Occupant
Excavator Equipment
Grader/scraper
Work Performed
Road Work
One Call Notified Ind
No
Locator Type
Unknown/other
Visible Marks
Unknown/other
Service Interruption
Yes
Service Interruption Hours
120
Root Cause Category
Notification Issue
Root Cause Type
No Notification Made To The One-Call Center/811
Preparer Name
J*** E* K*****
Preparer Title
Sr. Staff Engineer
Preparer Email
J******@e****.com
Preparer Telephone
7133814830
Preparer Fax
7133816660
Prepared Date
2012-02-27 00:00:00
Authorizer Name
J*** E* K*****
Authorizer Telephone
7133814830
Authorizer Title
Sr. Staff Engineer
Authorizer Email
J******@e****.com
Narrative
On july 5, 2010, a private landowner was performing road work on his property adjacent to a pond and within the dixie pipeline designated row. The landowner did not contact one-call and did not contact dixie. The landowner hit the 8-inch dixie pipeline on his property with his dozer. A gouge and split from the dozer that penetrated through the wall of the pipeline resulted in a release of propane that led to a subsequent explosion and fire. The landowner, who was operating the dozer, was injured by the release. One fatality resulted from the subsequent explosion and fire with additional property damage ensuing. The operator took immediate action to isolate the pipeline and reduce the impact to the public and the environment.
Report Received Date 2010-08-02 00:00:00
Iyear 2010
Report Number 20100163
Supplemental Number 16455
Report Type Supplemental Final
Operator Id 3445 PHMSA Enforcement
Name Dixie Pipeline
Operator Street Address 1100 Louisiana St.
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2010-07-05 10:40:00
Location Latitude 33.53866 Google Maps OpenStreetMap
Location Longitude -82.53516 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls 3104
Intentional Release Bbls 0
Recovered Bbls 0
Fatality Ind Yes
Num Emp Fatalities 0
Num Contr Fatalities 0
Num Er Fatalities 0
Num Worker Fatalities 0
Num Gp Fatalities 1
Fatal 1
Injury Ind Yes
Num Emp Injuries 0
Num Contr Injuries 0
Num Er Injuries 0
Num Worker Injuries 0
Num Gp Injuries 1
Injure 1
Accident Identifier Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime 2010-07-05 10:40:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2010-07-05 10:52:00
Restart Datetime 2010-07-10 11:52:00
On Site Datetime 2010-07-05 12:27:00
Nrc Rpt Datetime 2010-07-05 11:58:00
Nrc Rpt Num 946588 NRC Report How to search
Ignite Ind Yes
Explode Ind Yes
Upstream Valve Type Ind Automatic
Downstream Valve Type Ind Automatic
Num Pub Evacuated 1
Pipe Fac Name Dixie Pipeline
Segment Name 120
Onshore State Abbreviation Ga
Onshore Postal Code 30824
Onshore City Name Thomson
Onshore County Name Mcduffie
Designated Location Milepost/valve Station
Designated Name 817.11
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 36
Crossing No
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 8.625
Pipe Wall Thickness 0.188
Pipe Smys 52000
Pipe Specification Api 5l
Pipe Seam Type Erw - High Frequency
Pipe Manufacturer Stupp Corp.
Pipe Coating Type Coal Tar
Installation Year 1961
Manufactured Year 1961
Material Involved Carbon Steel
Release Type Mechanical Puncture
Puncture Axial 4.9
Puncture Circum 9.4
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 130124
Est Cost Prop Damage 345058
Est Cost Emergency 49093
Est Cost Environmental 0
Est Cost Other 0
Prpty 524275
Accident Psig 847
Mop Psig 1440
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 292512
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind Yes
Scada Conf Ind Yes
Cpm In Place Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Controller Ind Yes
Employee Drug Test Ind Yes
Contractor Drug Test Ind No
Num Employees Tested 1
Num Employees Failed 0
Cause Excavation Damage
Cause Details Excavation Damage By Third Party
Ex Party Type Excavation Damage By Third Party
Prior Notification Ind No
Notify Cga Dirt Yes
Pipeline Easement Row Ind Yes
Excavator Type Occupant
Excavator Equipment Grader/scraper
Work Performed Road Work
One Call Notified Ind No
Locator Type Unknown/other
Visible Marks Unknown/other
Service Interruption Yes
Service Interruption Hours 120
Root Cause Category Notification Issue
Root Cause Type No Notification Made To The One-Call Center/811
Preparer Name J*** E* K*****
Preparer Title Sr. Staff Engineer
Preparer Email J******@e****.com
Preparer Telephone 7133814830
Preparer Fax 7133816660
Prepared Date 2012-02-27 00:00:00
Authorizer Name J*** E* K*****
Authorizer Telephone 7133814830
Authorizer Title Sr. Staff Engineer
Authorizer Email J******@e****.com
Narrative On july 5, 2010, a private landowner was performing road work on his property adjacent to a pond and within the dixie pipeline designated row. The landowner did not contact one-call and did not contact dixie. The landowner hit the 8-inch dixie pipeline on his property with his dozer. A gouge and split from the dozer that penetrated through the wall of the pipeline resulted in a release of propane that led to a subsequent explosion and fire. The landowner, who was operating the dozer, was injured by the release. One fatality resulted from the subsequent explosion and fire with additional property damage ensuing. The operator took immediate action to isolate the pipeline and reduce the impact to the public and the environment.